INSP-Final Inspection | 9/20/2007 | 9/21/2007 | 9/21/2007 | A | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Final Inspection | 9/19/2007 | 9/20/2007 | 9/20/2007 | P | CANC |
Troy Cobbley
|
|
|
Please call 1/2 hour prior to inspection. Brian is the contact, thank you. Phone #: ###-#### Internet Inspection Request from: Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Final Inspection | 9/17/2007 | 9/17/2007 | 9/17/2007 | P | FAIL |
Troy Cobbley
|
|
|
The domestic bypass valve is not installed yet. The underground supply has not been flushed yet. The riser needs mounted to the wall. Adequate pipe stands need to be supplied at the riser. Pendant sprinkler heads are blocked by ceiling fans and light fixtures.Project is not ready for a final.
|
INSP-Final Inspection | 9/13/2007 | 9/14/2007 | 9/14/2007 | A | CANC |
Troy Cobbley
|
|
|
needs to be rescheduled per contractor
|
INSP-Final Inspection | 9/12/2007 | 9/13/2007 | 9/13/2007 | A | FAIL |
Troy Cobbley
|
|
|
The bell has not been installed yet. No inspection was performed will need to be rescheduled.
|
INSP-Final Inspection | 9/11/2007 | 9/12/2007 | 9/12/2007 | P | CANC |
Troy Cobbley
|
|
|
Please call 1/2 hour prior to inspection. Brian is the contact, thank you. Phone #: ###-#### Internet Inspection Request from: Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Final Inspection | 9/10/2007 | 9/10/2007 | 9/10/2007 | P | CANC |
Troy Cobbley
|
|
|
Brian F is the contact. Thanks Phone #: ###-#### Internet Inspection Request from: Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Sprinkler Rough-in/Hydro | 7/26/2007 | 7/27/2007 | 7/27/2007 | P | PASS |
Troy Cobbley
|
|
|
The sprinkler piping is ok to cover. There are some minor corrections required which can be verified at the final. As-built drawings will be required prior to a final that reflect the changes in the pipe routing and the additional heads.
|