INSP-Final Inspection | 7/26/2007 | 7/27/2007 | 7/27/2007 | A | PASS |
Forrest France
|
|
|
C/N items are completed, fire alarm permit finaled.
|
INSP-Final Inspection | 7/26/2007 | 7/26/2007 | 7/26/2007 | P | CANC |
Forrest France
|
|
|
No time available to complete this inspection.
|
INSP-Final Inspection | 7/25/2007 | 7/25/2007 | 7/25/2007 | P | PART |
Forrest France
|
|
|
Final pending as-built plans for field modifications, also need to test door holder interconnections when completed, provide updated map at the panel.
|
INSP-Final Inspection | 7/23/2007 | 7/24/2007 | 7/24/2007 | A | NR |
Forrest France
|
|
|
Project is not ready for inspection at this time due to fire sprinkler permit testing.
|
INSP-Final Inspection | 7/19/2007 | 7/20/2007 | 7/20/2007 | P | FAIL |
Troy Cobbley
|
|
|
The releasing panel would not trip the valve. The required second permit for the two panel interconnecton was not called in and was not tested. I did test the some of the smoke detectors and all of the manual pulls. But this test really should be started over.
|