Permit Information
Permit NumberFIR07-00546
StatusFinaled
Name ABSOLUTE FIRE PROTECTION
Site Address 11818 W JOPLIN RD
Project NameWEST BOISE WWTP
Customer Number 
ePlanReview 
Description
Scope of Work:
Fully sprinkle a new single story structure excluding the exterior overbuild entryways. The system will be controlled from a Wall PI valve located outside of the riser room located on the North East corner of the bldg. The Underground work was permitted separately from this permit.
The fire sprinkler system work shall comply with the IFC 2003, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to building permit: BLD05-02539. This permit s also attached to permit FIR07-00459 for Underground work.02/06/08 Revised Scope of Work:
These previously approved plans were resubmitted due to plan modifications which included adding 8 additional heads above the bathrooms and under the duct work. A 4” Wilkins 350A back flow device was installed in lieu of the approved 3” Ames back flow device. These changes altered the performance of the remote area of operation; as a result new calculations were submitted to support this modification. This modification was noted as a plan revision dated 02/06/08. A total of 24 heads were affected by this modification. This modification does not appear to adversely affect the remote area of operation.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection3/24/20083/24/20083/24/2008PPASS
DetailsTroy Cobbley
Permit finaled
INSP-Sprinkler Rough-in/Hydro3/17/20083/17/20083/17/2008PPASS
DetailsTroy Cobbley
The overhead piping hydro test passed. The sprinkler piping above the gridded ceilings is ok to cover.
INSP-Sprinkler Rough-in2/5/20082/5/20082/5/2008PPASS
DetailsTroy Cobbley
As-builts need to be provided showing the additional heads. Several heads need tape and foil removed. Provide aux. drain on west end of system as per plans. Provide the correct backflow or provide resubmittals for friction loss verification. Still need to hydro, forward flush and the other finishing touches.
INSP-Conference11/8/200711/9/200711/9/2007ADONE
DetailsTroy Cobbley
I spoke to mike, the superintendant, about the combustible concealed spaces located around the exterior of the building. They are required to be sprinklered per NFPA 4.1 unless the meet one of the exceptions of 8.14
FIR-Aging Inspection10/16/200710/16/200710/16/2007 NR
DetailsTroy Cobbley
Work is in progress