INSP-Final Inspection | 3/24/2008 | 3/24/2008 | 3/24/2008 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 3/17/2008 | 3/17/2008 | 3/17/2008 | P | PASS |
Troy Cobbley
|
|
|
The overhead piping hydro test passed. The sprinkler piping above the gridded ceilings is ok to cover.
|
INSP-Sprinkler Rough-in | 2/5/2008 | 2/5/2008 | 2/5/2008 | P | PASS |
Troy Cobbley
|
|
|
As-builts need to be provided showing the additional heads. Several heads need tape and foil removed. Provide aux. drain on west end of system as per plans. Provide the correct backflow or provide resubmittals for friction loss verification. Still need to hydro, forward flush and the other finishing touches.
|
INSP-Conference | 11/8/2007 | 11/9/2007 | 11/9/2007 | A | DONE |
Troy Cobbley
|
|
|
I spoke to mike, the superintendant, about the combustible concealed spaces located around the exterior of the building. They are required to be sprinklered per NFPA 4.1 unless the meet one of the exceptions of 8.14
|
FIR-Aging Inspection | 10/16/2007 | 10/16/2007 | 10/16/2007 | | NR |
Troy Cobbley
|
|
|
Work is in progress
|