Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberFIR07-00620
StatusFinaled
Name PHOENIX FIRE PROTECTION
Site Address 105 N 9TH ST
Project NameSONNA BLDG
Customer Number 
ePlanReview 
Description
To add/relocate 36 sprinklers to accomodate new tenant wall layout. NOTE: This work is part of TI project BLD07-00845 with the following scope: To perform interior and minor exterior work to expand an existing 1,653 sq.ft. office into an adjacent 2067 square feet retail space to bring the office to 3,760 square feet. To relocate the existing store front entry door to make an accessible entrance. NOTE: This building is fully fire sprinklered for substitution of one-hour fire-resistive construction. All construction shall be per the approved plans and attached comment list. CZC07-00076. MJP
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection9/24/20079/24/20079/24/2007PPASS
DetailsForrest France
Fire sprinkler passed final inspection, permit finaled.
INSP-Sprinkler Rough-in9/19/20079/20/20079/20/2007APART
DetailsForrest France
Remainder of the overhead rough-in is approved for cover as noted on stamped plan set.
INSP-Sprinkler Rough-in9/19/20079/19/20079/20/2007PCANC
DetailsForrest France
Overbooked.
INSP-Sprinkler Rough-in9/11/20079/12/20079/12/2007APART
DetailsForrest France
See approved plans for areas okay for cover at the hard lid ceilings.
INSP-Sprinkler Rough-in8/29/20078/30/20078/30/2007APART
DetailsForrest France
Required corrections noted at the previous inspection have been repaired, OH fire sprinkler modifications for phase one as noted on approved plans are okay for ceiling cover.
INSP-Sprinkler Rough-in8/29/20078/29/20078/29/2007PCANC
DetailsTroy Cobbley
Due to the abundance of inspections today there was not adequate time to perform this one. It will need to be rescheduled.
INSP-Sprinkler Rough-in8/22/20078/23/20078/23/2007AFAIL
DetailsForrest France
See approved plans for areas inspected and noted defficiences including overspaced heads at an office and equip. room, missing hangers at two arm-overs, and missing heads at three closets.