INSP-Final Inspection | 10/13/2008 | 10/14/2008 | 10/14/2008 | A | PASS |
Forrest France
|
|
|
All corrections made per last inspection. KR
|
INSP-Final Inspection | 9/17/2008 | 9/18/2008 | 9/18/2008 | A | FAIL |
Forrest France
|
|
|
Per contractor missing cold cavity protection, noted missing escutcheons, lacking tamper switches at the main control and backflow shutoff valves.
|
INSP-Sprinkler Rough-in/Hydro | 6/12/2008 | 6/12/2008 | 6/12/2008 | P | PART |
Forrest France
|
|
|
Final pending system fire alarm interconnection.
|
INSP-Sprinkler Rough-in/Hydro | 6/2/2008 | 6/3/2008 | 6/3/2008 | A | PART |
Forrest France
|
|
|
Overhead hydrostatic testing completed satisfactory for the new system piping.
|
INSP-Sprinkler Rough-in | 5/29/2008 | 6/2/2008 | 6/2/2008 | A | PASS |
Troy Cobbley
|
|
|
UG Flush and the forward flush passed.. I notified todd that the flow switch and tamper switches will need to be connected to the fire alarm system.
|
INSP-Sprinkler Rough-in | 5/15/2008 | 5/15/2008 | 5/15/2008 | P | PART |
Forrest France
|
|
|
Okay to cover underground supply line. Agreed to accept as-built plans for the deletion of the meter due to dedicated fire service.
|
INSP-Sprinkler Rough-in | 5/9/2008 | 5/9/2008 | 5/9/2008 | P | FAIL |
Forrest France
|
|
|
UG fire supply line is not approved for cover due to missing meter installation per plan, depth of bury does not meet min. requirements adjacent to the foundation.
|
INSP-Sprinkler Rough-in/Hydro | 12/13/2007 | 12/13/2007 | 12/13/2007 | P | PART |
Forrest France
|
|
|
Missing one head at the pantry, remainder of the OH rough-in is acceptable, riser is not yet built, need to provide cold cavity protection as detailed.
|