Permit Information
Permit NumberFIR07-00737
StatusFinaled
Name IDAHO FIRE PROTECTION
Site Address 824 W IDAHO ST
Project NameBLOCK 44
Customer Number 
ePlanReview 
Description
Scope of Work: Overhead & Underground
Beginning from an existing 6” supply at first flange above the finished floor inside the south end of the basement. The Underground scope of work including a Post Indicating Valve was done by others also located on the South side of the Bldg. The overhead fire sprinkler scope of work includes installing three 4” wet risers to serve each of the three levels through out the entire 25,565-ft/2 vanilla shell bldg. The fire sprinkler system work shall comply with the IFC 2003, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to building permit: BLD07-01386, BLD02-00542 & UG permit FIR02-00442.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection1/10/20081/10/20081/10/2008APASS
DetailsForrest France
Scope of work for this permit finaled. see FIR07-00913 for over head work and additional comments. KR
INSP-Final Inspection1/8/20081/9/20081/9/2008ANR
DetailsForrest France
Need project related fire alarm permit work inspection.
INSP-Sprinkler Rough-in/Hydro12/19/200712/19/200712/19/2007PPART
DetailsForrest France
OH hydrostatic test for the basement and 2nd floor wet systems passed inspection.
INSP-Sprinkler Rough-in/Hydro12/12/200712/12/200712/12/2007PPART
DetailsForrest France
Over head hydro 1st floor passed.See approved set of plans for any red lined areas.KR
INSP-Sprinkler Rough-in/Hydro11/30/200711/30/200711/30/2007PPART
DetailsForrest France
See approved plan set for areas inspected today.
INSP-Conference10/1/200710/1/200710/1/2007ADONE
DetailsForrest France
On site conference to discuss project shell and tenant work interface, also discussed second floor ceilings.