INSP-Final Inspection | 11/7/2007 | 11/8/2007 | 11/8/2007 | P | PASS |
Forrest France
|
|
|
Do a full function test on preaction system.Verifie flow, tamper and alarm to main panel and clean agent fike panel.
|
INSP-Sprinkler Rough-in/Hydro | 11/7/2007 | 11/7/2007 | 11/7/2007 | P | CANC |
Forrest France
|
|
|
javier Phone #: ###-####
|
INSP-Sprinkler Rough-in/Hydro | 10/4/2007 | 10/5/2007 | 10/5/2007 | A | PART |
Forrest France
|
|
|
Pneumatic testing for the preaction system passed.
|
INSP-Sprinkler Rough-in/Hydro | 10/3/2007 | 10/4/2007 | 10/4/2007 | A | PART |
Forrest France
|
|
|
Added heads below ductwork are acceptable, okay for cover at the drop ceilings, begin pneumatic testing @ 40psi at 10:15 AM for the preaction system.
|
INSP-Sprinkler Rough-in/Hydro | 9/21/2007 | 9/24/2007 | 9/24/2007 | A | PART |
Forrest France
|
|
|
OH rough-in for the new preaction and wet systems completed, noted blocked heads by ductwork over 4' in width will require added heads at five locations, riser is not completed at this time, areas at the drop ceilings are okay for cover, AG hydrostatic testing passed, need to perform 24 hr. pneumatic test on the preaction system.
|