Permit Information
Permit NumberFIR07-00766
StatusFinaled
Name COMMERCIAL FIRE PROTECTION
Site Address 4162 W QUAIL HILL CT
Project NameBlaser Residence
Customer NumberSEE COMMENTS
ePlanReview 
Description
Scope of Work - Beginning from the discharge side of the 1 ¼” back flow device, install a new CPVC fire sprinkler system through out the two story 12,372-ft/a single family dwelling including a high temp head to be located in the Sauna Rm. The system shall be equipped with an alarm initiating device and an outside alarm. The system shall be modified to include coverage in the two garages along the common walls as directed by the bldg. department. All fire sprinkler work and related, which includes dual use, single service water supply, the system backflow prevention device (provided by others), shall be per NFPA 13D Modified, approved plans, engineering/red-lining and attached review comments, under direction of the Fire Chief. This permit is attached to BLD07-00142.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection12/10/200812/10/200812/11/2008PPASS
DetailsTroy Cobbley
Permit finaled
INSP-Sprinkler Rough-in/Hydro12/9/200812/9/200812/9/2008PPASS
DetailsTroy Cobbley
Permit finaled
INSP-Final Inspection12/2/200812/2/200812/2/2008PCANC
DetailsTroy Cobbley
Phone #: ###-#### Internet Inspection Request from: John Warnick
INSP-Sprinkler Rough-in/Hydro11/26/200811/26/200811/26/2008PFAIL
DetailsTroy Cobbley
Flow switch has not been wired to the alarm bell, not all ceilings have been finished, missing escheons and exposed cpvc piping under the east basement stairs. Also a sprinkler head at the top of the west stairs, first floor, needs to be relocated away from a can light or an intermediate temperature head needs to be installed as per 7.5.5.3 of NFPA 13D.
INSP-Final Inspection11/24/200811/25/200811/25/2008ACANC
DetailsTroy Cobbley
vance Phone #: ###-#### Inspection cancelled from web by: John Warnick
INSP-Final Inspection4/1/20084/2/20084/2/2008PFAIL
DetailsTroy Cobbley
Project was not complete. Ceiling finishes had not been completed yet (both painted and wood). I noted to the sprinkler contractor several sprinkler esch. that had been painted. Bell was not installed yet.
INSP-Final Inspection4/1/20084/2/20084/1/2008ACANC
DetailsTroy Cobbley
terry Phone #: ###-#### Inspection cancelled from web by: John Warnick
INSP-Supply line flush1/10/20081/10/20081/10/2008PPASS
DetailsTroy Cobbley
Underground flush passed.
INSP-Sprinkler Rough-in/Hydro10/26/200710/29/200710/29/2007PPASS
DetailsTroy Cobbley
Sprinkler piping is ok to cover. I let the builder and on a previous visit the owner know my concerns that the tenting is maintained and that adequate insulation is provided.
INSP-Sprinkler Rough-in10/25/200710/26/200710/26/2007AFAIL
DetailsTroy Cobbley
The tenting is still inadequate in areas. I did not find the framer when I was on site but the builder called me later and I let him know the areas of concern. He will fix these and call it back in for monday.
INSP-Sprinkler Rough-in10/25/200710/25/200710/26/2007PCANC
DetailsTroy Cobbley
Overbooked with micron
INSP-Sprinkler Rough-in10/23/200710/24/200710/24/2007PFAIL
DetailsTroy Cobbley
There are still major tenting issues. I went over them with the fire sprinkler contractor and the framer.
INSP-Sprinkler Rough-in/Hydro10/15/200710/16/200710/16/2007PFAIL
DetailsTroy Cobbley
See the city approved plans for locations where sprinkler pendants and sidewalls are overspaced. The tenting is inadequate and/or missing in many locations. Also the piping in supposed heated areas is open to unheated areas. In several locations the piping has been rerouted and additional heads have been added due to architectural features. Provide asbuilt plans prior to cover approval.