INSP-Final Inspection | 11/27/2007 | 11/27/2007 | 11/27/2007 | P | PASS |
Troy Cobbley
|
|
|
overhead finaled, new set of city approved plans on site with all changesmade and approved..Per KR
|
INSP-Sprinkler Rough-in/Hydro | 11/16/2007 | 11/16/2007 | 11/16/2007 | A | FAIL |
Troy Cobbley
|
|
|
Overhead hydro test passed. The doghouses need inspected still. One head needs to be added between the two kitchen hoods. Two heads need to be extended in the north dining area to provide coverage under a soffit/decorative beam. Sprinkler coverage needs to be added in the new shed that is attached to the main building. The sprinkler contractor needs to contact Brian about installing galvanized piping on the roof of the structure for the additional dog house and the addition of the sprinkler head in the shed.
|