Information based on query as of Sunday, June 30, 2024.
Permit Information
Permit NumberFIR07-00825
StatusFinaled
Name DEBEST FIRE PROTECTION
Site Address 641 W MCGREGOR DR Unit: 106
Project NameFederal Way Commerce - #3
Customer Number 
ePlanReview 
Description
The Permitted Work Scope: Over Head Only
Modify the existing system by adding and relocating heads on the second floor to accommodate a new ceiling layout. The first floor open office area will be protected by a new piping and sprinkler layout per NFPA 13. No additional sectional control valves will be required. The fire sprinkler system work shall comply with the IFC 2003, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to BLD07-01562.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection12/13/200712/13/200712/13/2007PPASS
DetailsForrest France
Permit finaled.
INSP-Final Inspection12/12/200712/13/200712/13/2007APASS
DetailsForrest France
Fire sprinkler passed final inspection, permit finaled.
INSP-Sprinkler Rough-in12/3/200712/4/200712/4/2007APART
DetailsForrest France
Noted correction item from the previous inspection has been completed, OH rough-in is acceptable.
INSP-Sprinkler Rough-in11/30/200712/3/200712/3/2007APART
DetailsTroy Cobbley
The office sprinkler piping is ok to cover but an additional upright head needs added by the overhead door where existing coverage is blocked.
INSP-Sprinkler Rough-in11/30/200711/30/200712/3/2007PCANC
DetailsTroy Cobbley
OH Cover inspection
Phone #: ###-#### x1234 Internet Inspection Request from: Alicia Pauley