Permit Information
Permit NumberFIR07-00874
StatusFinaled
Name SIMPLEX/GRINNELL
Site Address 1130 N ALLUMBAUGH ST
Project NameValley View-Assisted Living
Customer Number 
ePlanReview 
Description
06/10/08 Conditions of Approval:
The existing air compressor shall meet the dry system 30 minute recovery time as required, or be replace with a new compressor the would meet the recovery time. To be field verified.
The combined air capacity of the new dry piping and the existing exceeds 750 gal of volume. A quick opening device is required in accordance with NFPA 13 7.2.3. To be field verified.
Add a forward flow assembly at the riser. (NFPA 10.10.2.5) To be field verified.
Independent living 07-01031 change out existing standard to quick response heads in the existing corridors, new construction and remolded areas only. Existing standard response shall remain in all other areas. See Attached Campbell & Associates, Inc. letter dated 05/20/08.
All heads affected with in the scope of work shall meet current code requirements for obstructions in accordance with NFPA 13 8.6.5. To be field verified. overheadScope of WORK
The scope if work include demolition of existing piping in the Dining area, adding and relocating new quick response heads in the existing corridors and adding a new system in the new construction area’s. The attic dry system will be modified to protect new areas and overbuilds. Attic heads will be installed.
The fire sprinkler system work shall comply with the IFC 2003, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to building permit: BLD07-01845
12/18/07 Conditions of Approval:
Replace the existing standard response heads through out the occupant rooms and corridors with new quick response heads to meet code. Resubmit an As-Built to include the additional heads and a revised head count. To be field verified.
Add a forward flow assembly at the riser. To be field verified.
The existing air compressor shall meet the dry system 30 minute recovery time as required, or be replace with a new compressor the would meet the recovery time. To be field verified.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection4/28/20094/28/20094/28/2009PPASS
DetailsTroy Cobbley
permit finaled
INSP-Final Inspection4/27/20094/28/20094/28/2009APASS
DetailsTroy Cobbley
Permit finaled
INSP-Sprinkler Rough-in4/6/20094/7/20094/7/2009APASS
DetailsTroy Cobbley
See the city approved plans for locations where the sprinkler piping can be covered. It will have todays date.
INSP-Sprinkler Rough-in/Hydro3/16/20093/17/20093/17/2009APASS
DetailsTroy Cobbley
Above ground hydro test for ALF canopy on the south side of the building passed.
INSP-Sprinkler Rough-in3/2/20093/3/20093/3/2009PPASS
DetailsTroy Cobbley
See the city approved plans for the canopy on the southwest corner of the building where the piping is ok to cover.
INSP-Final Inspection12/11/200812/12/200812/12/2008PPART
DetailsTroy Cobbley
The new Dining Room and the Aid Station areas sprinkler system is complete.
INSP-Sprinkler Rough-in/Hydro11/20/200811/21/200811/21/2008AFAIL
DetailsForrest France
Inspection for the aid station room only passed as initialed and red lined on plans, also noted one overspaced head and one obstructed head at the adjacent common corridor-see red line annotations.
INSP-Final Inspection11/20/200811/20/200811/20/2008PNH
DetailsForrest France
No access to complete inspection.
INSP-Sprinkler Rough-in11/3/200811/4/200811/4/2008APART
DetailsTroy Cobbley
The above ground hydro test for the new dining room passed and the piping can be covered.
INSP-Sprinkler Rough-in/Hydro10/31/200811/3/200811/3/2008PFAIL
DetailsTroy Cobbley
steven Phone #: ###-#### The contact phone number is wrong so I went to the job site and did not make contact in person. I called the field supervisor todd but could only leave a message on voice mail. Also the plans at the pipe machine are not the city approved. No inspection was performed and will need to be rescheduled.
INSP-Sprinkler Rough-in10/28/200810/29/200810/29/2008PPART
DetailsForrest France
The overhead install at the dining area appears acceptable however pipe sizing does not match approved plan set on site, contractor to provide stamped drawings reflecting the accurate sizing prior to approval for cover, relocated heads at the existing corridors okayed with the exception of one overspaced head and one armover missing a hanger.
INSP-Sprinkler Rough-in10/21/200810/22/200810/22/2008PPART
DetailsTroy Cobbley
No approved plans were presented but I gave approval to cover the piping in the narrow soffict in the new dining room.
INSP-Sprinkler Rough-in6/26/20086/27/20086/27/2008PCANC
DetailsForrest France
james Note: cover up Phone #: ###-#### Inspection cancelled from web by: Alexandra Rahn
INSP-Sprinkler Rough-in6/19/20086/20/20086/20/2008APASS
DetailsTroy Cobbley
See the city approved plans for the sprinkler piping in the one overbuild that is ok for cover. The connection into the existing dry system is not complete and has been marked as such on the plans.
INSP-Final Inspection6/17/20086/19/20086/19/2008APART
DetailsTroy Cobbley
The fire sprinkler work for the two room west addition and the ten room west addition is complete. 401 canopies have been added at al of the heads that were in conflict with the lights. Jim is to provide 401 canopies for the two pendants that were in the locked closets and change the sidewall heads in the corridor ceiling pockets to quick responce. I will verify this work at the next inspection. Also the sprinkler piping in the connecting corridor, as marked on the approved plans, is ok to cover. This piping has not been connected to the dry system yet and will need to be verified at a later time.
INSP-Sprinkler Rough-in6/9/20086/10/20086/10/2008ADONE
DetailsTroy Cobbley
This inspection was actually for a conference regarding the light fixtures blocking the pendant sprinkler spray. Grinnell did not show up for the conference but the superintendant for Petra was there and he made a copy of the Beam Rule spacing chart in NFPA 13 cahpter 8. We measured a couple of heads so that he knew what I was looking at.
INSP-Sprinkler Rough-in/Hydro6/6/20086/6/20086/6/2008PPASS
DetailsTroy Cobbley
24 hour air test for the Dining Area and the Aid Station has passed
INSP-Sprinkler Rough-in/Hydro6/4/20086/5/20086/5/2008APART
DetailsTroy Cobbley
The 24 hour air tests have been started for the Aid Station with 42psi on the guage and the Dining Area with 47psi on the guage. Test started at 9:00am
INSP-Sprinkler Rough-in/Hydro6/3/20086/4/20086/4/2008PPASS
DetailsTroy Cobbley
The dry system hydro test for the Aid Station and the Dining area passed.
INSP-Sprinkler Rough-in/Hydro5/28/20085/30/20085/30/2008APART
DetailsTroy Cobbley
The 24 hour air test on the ALF passed but it failed on the Nurses Station.
INSP-Sprinkler Rough-in/Hydro5/28/20085/29/20085/29/2008ADONE
DetailsTroy Cobbley
The 24 hour air test was begun with 42psi on both the ALF and the Nurses Station dry systems at 8:15am. It also appears that many of the pendant heads do not meet the three times rule from the light fixtures.
INSP-Sprinkler Rough-in/Hydro5/28/20085/28/20085/28/2008PPASS
DetailsTroy Cobbley
The overhead hydro test of the ALF dry system passed.
INSP-Sprinkler Rough-in5/19/20085/20/20085/20/2008APASS
DetailsTroy Cobbley
The AOF dining area dry system is ok to cover.
INSP-Sprinkler Rough-in/Hydro5/13/20085/14/20085/14/2008PCANC
DetailsTroy Cobbley
Per stephen the dry system hydro test failed due to a dry pendant. Will be rescheduled.
INSP-Sprinkler Rough-in/Hydro5/12/20085/13/20085/13/2008APASS
DetailsTroy Cobbley
The 24 hour air test on the west dry system passed.
INSP-Sprinkler Rough-in/Hydro5/9/20085/12/20085/12/2008APART
DetailsTroy Cobbley
The east wet system hydro test passed. The west wet system hydro test passed. The west dry system 24 hour air test was started at 9:30. I took two time to pass the hydro tests today.
INSP-Sprinkler Rough-in/Hydro5/7/20085/9/20085/9/2008APART
DetailsTroy Cobbley
The hydro test of the south wing dry system passed. The hydro test of the south wing wet system failed.
INSP-Sprinkler Rough-in1/31/20082/1/20082/1/2008APASS
DetailsTroy Cobbley
The piping rough-in for the wet and dry systems in the new northwest wing are passed. The tenting of the pipe is not complete. No piping can be covered yet.
INSP-Sprinkler Rough-in1/30/20081/30/20081/30/2008PPASS
DetailsTroy Cobbley
The tenting/insulation for the south wing is acceptable. Piping still can not be covered since the stop work order for the fire alarm system still stands.
INSP-Sprinkler Rough-in1/28/20081/29/20081/29/2008PPART
DetailsTroy Cobbley
The rough-in for the piping in the south wing matches the as-built plans except for the two starter pieces for the branchlines at the building connection. Plans indicate 2" starter pieces but the size installed is 1 1/2". The tenting is not complete yet.
INSP-Sprinkler Rough-in1/24/20081/25/20081/25/2008PFAIL
DetailsTroy Cobbley
Todays inspection was for the wet system. I failed it because the plans and hydraulic calculations state the max spacing is to be 196sq ft per head. The installation and the piping plans show the heads at nearly 225sq. ft. I contacted Brian. The plans need to be resubmitted prior to the next inspection for verification that the greater spacing is hydraulically supported.
INSP-Sprinkler Rough-in1/22/20081/24/20081/24/2008PFAIL
DetailsTroy Cobbley
I arrived at the job site and was notified that the project was not ready for my re-inspection.
INSP-Sprinkler Rough-in1/15/20081/18/20081/18/2008PPART
DetailsTroy Cobbley
The attic system rough-in in the south wing is passed. Per jim and I's discussion it will be ok to provide a 1" drain from the 2 1/2" branchline to the 4" main. Through bolts are required on all of the earthquake attachments. The dry piping in the overbuilds has not been installed yet nor has the 4" tie in.