Permit Information
Permit NumberFIR07-00896
StatusFinaled
Name SIMPLEX/GRINNELL
Site Address 101 S CAPITOL BLVD
Project NameSPR-US Bank 12 th Floor
Customer Number 
ePlanReview 
Description
To add and relocate SSP's to new ceiling and wall layout in elevator lobby and core area.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection2/5/20082/6/20082/6/2008PPASS
DetailsForrest France
Fire sprinkler permit finaled.
INSP-Sprinkler Rough-in1/4/20081/7/20081/7/2008APASS
DetailsTroy Cobbley
Sprinkler piping in the lobby area is ok to cover. One head needs to be brought out to provide adequate spacing as discussedl. This will be checked at the final.
INSP-Sprinkler Rough-in/Hydro11/13/200711/15/200711/15/2007APASS
DetailsTroy Cobbley
The sprinkler piping in the lobby is ok to cover