Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberFIR07-00902
StatusFinaled
Name DEBEST FIRE PROTECTION
Site Address 1649 W SHORELINE DR
Project NameAssociated General Contractors
Customer Number 
ePlanReview 
Description
overheadScope of Work: Overhead Only
Under a separate permit, the Underground scope of work included connecting to an existing 6” C-900 capped line located at the property line which was provided by others. Run the new 220’-6” section of 6” C-900 out and up into the 1 hour rated riser room. Under this FIR permit, the overhead fire sprinkler scope of work includes installing a 3” wet riser and a 3” back flow device. Two separate risers will serve through out this two story office Bldg. shell.. The first and second floors supplies will be controlled separately. Ant future TI work shall be submitted under a separate permit. The fire sprinkler system work shall comply with the IFC 2003, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to building permit: BLD07-01248 & UG permit FIR07-00894.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection7/17/20087/17/20087/17/2008PPASS
DetailsForrest France
Noted correction items are complete, fire sprinkler permit finaled.
INSP-Supply line flush7/16/20087/17/20087/17/2008PDEFR
DetailsForrest France
Duplicate inspection request-flush completed, final inspection scheduled.
INSP-Final Inspection7/16/20087/16/20087/16/2008PFAIL
DetailsTroy Cobbley
Surface mounted lights in both of the first floor and second floor janitor closets and the second floor elevator room are blocking the sprinkler pendants. Also the riser room is required to be one hour rated but has holes and a block out for a ceiling mounted access panel.
INSP-Alarm Testing7/15/20087/16/20087/16/2008ACANC
DetailsTroy Cobbley
Wrong inspection type called in.
INSP-Alarm Testing7/14/20087/15/20087/15/2008ACANC
DetailsForrest France
Wrong inspection request type-"alarm testing" to be completed in conjunction with the project related FIR permit called in for afternoon inspection.
INSP-Alarm Testing7/11/20087/14/20087/14/2008PCANC
DetailsTroy Cobbley
The fire sprinklers where not quite ready when I was there to do the inspection. Will be rescheduled for tomorrow morning.
INSP-Sprinkler Rough-in/Hydro7/11/20087/14/20087/14/2008APASS
DetailsTroy Cobbley
OH Hydro Inspection for the first floor passed
INSP-Sprinkler Rough-in/Hydro7/10/20087/11/20087/11/2008APASS
DetailsTroy Cobbley
OH Hydro Inspection for the second floor passed.
INSP-Conference7/10/20087/10/20087/10/2008PDONE
DetailsTroy Cobbley
The conference was for the curved clouds in the first floor corridor. It appears that the way dave wants to install the sprinkler heads is acceptable and that floor coverage is being met.
INSP-Sprinkler Rough-in6/30/20087/1/20087/1/2008APART
DetailsForrest France
Forward flow of the DCVA backflow preventer completed satisfactory.
INSP-Sprinkler Rough-in/Hydro6/24/20086/26/20086/26/2008PPART
DetailsForrest France
Hydrostatic testing for the FDC piping completed satisfactory.
INSP-Sprinkler Rough-in/Hydro6/24/20086/26/20086/26/2008APART
DetailsForrest France
Overhead fire sprinkler install is good for cover at the drop ceiling areas 1st floor and restrooms 2nd floor, reinspected noted defficiencies from the previous visit.
INSP-Sprinkler Rough-in6/19/20086/19/20086/19/2008PPASS
DetailsTroy Cobbley
The sprinkler piping at the top of the east stair well can be covered. This was the extent of todays inspection. The plans were not marked.
INSP-Sprinkler Rough-in5/29/20085/30/20085/30/2008APART
DetailsTroy Cobbley
This inspection was for a first floor rough-in. The sprinkler piping can not be covered yet since final locations for the pendants is not done. No t-bar has been installed yet. The rough-in for the most part is ok. Two items have been noted. They include most of the branchline hangers to the north of the 3" main have been attached to the bottom of the beams. I referenced note #50 which does not allow this. Also the sidewall head installed at the top of the elevator shaft has not been installed in the 4" to 6" window.
INSP-Sprinkler Rough-in5/27/20085/27/20085/27/2008PFAIL
DetailsForrest France
Pendent head at the mechanical room 2nd floor is obstructed by an adjacent duct-need to relocate as discussed, remainder of hard lid ceilings are good for cover.
INSP-Sprinkler Rough-in/Hydro4/28/20084/28/20084/28/2008APART
DetailsForrest France
See locatons on approved plans set for rough-in areas inspected and okayed to date, noted shell protection sprig-ups at the common corridor 2nd floor are not installed-heads at this area may coincide with tenant permit work depending on job schedule.
INSP-Sprinkler Rough-in4/23/20084/25/20084/25/2008PPART
DetailsForrest France
OH rough-in inspection completed for the second floor only at this time, see plans for areas not completed to date.
FIR-Aging Inspection2/13/20082/13/20082/13/2008 DEFR
DetailsForrest France
Site visit- building is under construction, work in progress.