Information based on query as of Friday, July 5, 2024.
Permit Information
Permit NumberFIR07-00935
StatusFinaled
Name AMERICAN FIRE PROTECTION LLC
Site Address 251 W GOWEN RD
Project NameWestern Trailers
Customer Number 
ePlanReview 
Description
Revised Scope of Work:
The contractor made revisions in the field during construction that resulted in complete resubmittal of the calculations and piping plan. The revisions included pipe size changes and adjustments to the hydraulic and seismic calculations. The revision is dated 06/27/08 and noted to be Rev 1. The original plans were approved with conditions on 12/07/07. During the second review, all of the original conditions of approval were verified for compliance. Scope of Work:
To install a complete wet pipe system in a new 55,415-ft/2, two story building designed for parts storage. This building is fully fire sprinklered. The fire sprinkler system work shall comply with the IFC 2003, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. The underground supply was permitted separately under FIR07-00812. Both this and the underground permits are attached to building permit: BLD07-01884.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection7/14/20087/15/20087/15/2008APASS
DetailsForrest France
Chain and lock was added to PIV. New set of resubmitted plans were on site with all corrections made. KR
INSP-Final Inspection7/9/20087/10/20087/10/2008AFAIL
DetailsForrest France
Plans are still under review for resubmittals.Fire sprinkler Inspection completed. One remaining item.Chain and lock is required on PIV. KR
INSP-Sprinkler Rough-in/Hydro6/20/20086/20/20086/20/2008PPART
DetailsForrest France
Verified some items per the C/N are finished including added heads at the wash bay, added seismic brace, spacing at the compressor room. Noted fire alarm work is nearly complete including tamper and flow switch wiring and FACP installation prior to the issuance of a fire alarm permit. Double permit fees will apply.
INSP-Sprinkler Rough-in/Hydro6/12/20086/12/20086/12/2008PPART
DetailsForrest France
OH hydrostatic testing for both wet systems passed. OH rough-in failed due to overspaced heads at the wash bay, blocked heads at the compressor room, missing EQ brace at the 4" main NE corner of the warehouse, need to provide resubmittals for pipe size changes at the north office areas, some finish items at the riser are not complete including flex. couplings, FDC ball drip, head box, tagged DCVA, etc.
INSP-Sprinkler Rough-in5/30/20086/3/20086/3/2008PPART
DetailsForrest France
1st and 2nd floor south offices OH rough-in is approved for cover with the exception of one missing EQ brace at the 2nd floor 3" main east side last piece.
INSP-Sprinkler Rough-in4/11/20084/14/20084/14/2008APASS
DetailsTroy Cobbley
The restroom, shower & locker room area are ok to cover. See the city approved plans for locations.
INSP-Sprinkler Rough-in/Hydro3/25/20083/25/20083/25/2008PNR
DetailsForrest France
Not completed for inspection.
FIR-Aging Inspection3/20/20083/20/20083/20/2008 DEFR
DetailsForrest France
Work in progress, construction underway.