Permit NumberFIR07-00937
StatusFinaled
Name COMMERCIAL FIRE PROTECTION
Site Address 2580 W WILLIAMSPORT LN
Project NameVISTA FOURPLEX
Customer Number 
ePlanReview 
Description
Scope of Work: To install a fire life safety NFPA 13R system to prevent flashover (total involvement) in the room of fire origin, where sprinklered, and to improve the chance for occupants to escape or be evacuated, in a new 5,556-ft/2 three story, four unit apartment building starting at the top of a 2” Ames Series 007 Backflow Double Check control. System shall be equipped with an alarm initiating device connected to an alarm system and an outside annunciating devise. All fire sprinkler work and related, which includes a dedicated service underground water supply, the system backflow prevention device, shall be per NFPA 13R, approved plans, engineering/red-lining and attached review comments, under direction of the Fire Chief. This permit is attached to: BLD06-02528. Revised Scope of Work: These previously approved plans and calculations were resubmitted due to changes made during construction that affected the remote area of operation. The modifications include adding 4 pendants, two on each level to meet code compliance. The two dry HSW heads second floor serving the decks were relocated. In addition, a second feed main to the second floor from the first was added. Design area 1 was affected. These modifications of the plans as they were approved do not appear to adversely affect the systems operation. The revisions are noted as 1 -6 and dated 03-04-08.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection3/18/20083/19/20083/19/2008APASS
DetailsTroy Cobbley
Permit finaled
INSP-Final Inspection3/17/20083/18/20083/18/2008AFAIL
DetailsForrest France
Provide service tag at the riser, provide "911" sign at the outside bell, missing escutcheons at some locations, one blocked head at a kitchen area by an adjacent light fixture.
INSP-Sprinkler Rough-in/Hydro3/17/20083/17/20083/17/2008PPART
DetailsForrest France
UG fire supply line hydrostatic test completed satisfactory.
INSP-Supply line flush3/17/20083/17/20083/17/2008PPART
DetailsForrest France
UG fire supply line flush completed in conjunction with United Water company.
INSP-Sprinkler Rough-in2/20/20082/21/20082/21/2008ACANC
DetailsForrest France
Per bruce.
INSP-Sprinkler Rough-in/Hydro12/24/200712/26/200712/26/2007APART
DetailsForrest France
Verified tenting installation at the third floor. OH fire sprinkler piping is okay for cover pending satisfactory plan resubmittals reflecting field modifications in piping layout including main/branch lines and changed head locations.
INSP-Sprinkler Rough-in12/24/200712/24/200712/24/2007PPART
DetailsForrest France
OH hydrostatic retest completed and passed per inspection done 12/21. No access provided to perform inspection for cover at the third floor today, noted insulation at the third floor does not appear to be finished at this time.
INSP-Sprinkler Rough-in/Hydro12/18/200712/19/200712/19/2007AFAIL
DetailsForrest France
OH Hydrostatic test failed due to 25 psi. pressure loss at the guage.
INSP-Sprinkler Rough-in12/17/200712/17/200712/18/2007PNR
DetailsForrest France
bruce - please call 1/2 hr prior to inspection Phone #: ###-####
INSP-Sprinkler Rough-in12/13/200712/14/200712/14/2007AFAIL
DetailsForrest France
Noted significant changes regarding the actual installation v. approved plans (main and branchline changes, supply riser changes, added heads, relocated sw heads, etc.), noted missing heads at closets on the 2nd floor, missing heads under the stairs 1st floor, added heads in mech, closets, branchline changes at the design area, noted the UG supply has been installed and covered without an inspection and will not be accepted until conditions of approval are met.
INSP-Sprinkler Rough-in12/13/200712/13/200712/13/2007PCANC
DetailsForrest France
Inspection to be rescheduled as discussed, noted contractor has been issued the permit and called for a system rough-in inspection the same day.