Permit Information
Permit NumberFIR07-00957
StatusFinaled
Name DEBEST FIRE PROTECTION
Site Address 3321 S FEDERAL WAY
Project NameWESTSIDE BODY WORKS
Customer Number 
ePlanReview 
Description
overheadThe Permitted Work Scope: Over Head Only
Add sprinkler coverage in the auto paint spray, mixing rooms and the prep area within this existing sprinkled bldg. These new areas are listed and self contained. The existing riser will be modified to include the new 6” riser manifold and BFP. Each self contained unit will have its own supply control valve. The valves are required top be supervised. The fire sprinkler system work shall comply with the IFC 2003, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to BLD07-02761. When tenant work affects fire sprinkler protection outside the permitted work area due to the installation of tenant-demising or new partition walls, the affected area sprinkler coverage outside the BLD permit will fall under the Fire Permit scope of work, to maintain the required fire protection within the fire sprinklered facility. The “Riser” and its supplies which include all appurtenances (including tamper, alarm and alarm monitoring) relating to the normal and correct function and integrity of this system will fall under the jurisdiction for code compliant verification.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection1/14/20081/14/20081/14/2008PPASS
DetailsForrest France
Corrections verified for compliance, fire sprinkler permit finaled.
INSP-Final Inspection1/11/20081/11/20081/11/2008PCANC
DetailsForrest France
Overbooked.
INSP-Sprinkler Rough-in/Hydro1/3/20081/4/20081/4/2008APART
DetailsForrest France
OH hydrostatic testing passed, also inspected overhead rough-in and noted some issues including missing flex couplings at the riser, need bags at the heads in the paint and spray booths, provide retaining straps at the beam clamps, need to certify DCVA, noted 286 deg. heads have been installed in lieu of 200 deg. as indicated on plans, the two DSW heads at the exhaust ducts are not yet installed.
INSP-Sprinkler Rough-in12/26/200712/27/200712/27/2007APART
DetailsForrest France
On site conference regarding head spacing at one spray booth to avoid cold soldering, no other items reviewed or inspected today.