INSP-Final Inspection | 2/23/2009 | 2/23/2009 | 2/23/2009 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 2/18/2009 | 2/19/2009 | 2/19/2009 | A | PART |
Forrest France
|
|
|
See inspection comments per T. Frost.
|
INSP-Final Inspection | 2/17/2009 | 2/18/2009 | 2/18/2009 | A | PART |
Forrest France
|
|
|
Sprinkler system interconnections to the fire alarm panel for trouble, supervisory, and alarm conditions completed satisfactory.
|
INSP-Sprinkler Rough-in/Hydro | 12/29/2008 | 12/29/2008 | 12/29/2008 | P | PART |
Forrest France
|
|
|
1st floor install okay for cover only as noted on approved plans.
|
INSP-Sprinkler Rough-in/Hydro | 12/12/2008 | 12/12/2008 | 12/12/2008 | A | PART |
Forrest France
|
|
|
Pneumatic dry systems test complete.
|
INSP-Sprinkler Rough-in/Hydro | 12/10/2008 | 12/11/2008 | 12/11/2008 | P | PART |
Forrest France
|
|
|
24 hr. air testing completed and passed for both dry systems.
|
INSP-Sprinkler Rough-in/Hydro | 12/10/2008 | 12/10/2008 | 12/10/2008 | A | PART |
Forrest France
|
|
|
Begin 24 hr. pneumatic testing for both dry systems each at 41psig @12:40.
|
INSP-Sprinkler Rough-in/Hydro | 12/1/2008 | 12/1/2008 | 12/1/2008 | A | PART |
Forrest France
|
|
|
|
INSP-Sprinkler Rough-in/Hydro | 11/28/2008 | 11/28/2008 | 11/28/2008 | P | PART |
Forrest France
|
|
|
Okay to cover 1st floor rough-in per plan annotations.
|
INSP-Sprinkler Rough-in/Hydro | 11/24/2008 | 11/25/2008 | 11/25/2008 | A | PART |
Forrest France
|
|
|
1st floor wet system hydrostatic testing passed, plan resubmittals verified for changes at the overhead install for the first floor as well- okay for ceiling cover-see initialed area on plans.
|
INSP-Supply line flush | 11/19/2008 | 11/19/2008 | 11/19/2008 | A | PART |
Forrest France
|
|
|
UG FDC piping flush completed acceptable.
|
INSP-Sprinkler Rough-in/Hydro | 11/19/2008 | 11/19/2008 | 11/19/2008 | A | PART |
Forrest France
|
|
|
Standpipe and remote FDC piping hydrostatic testing completed satisfactory.
|
INSP-Supply line flush | 11/12/2008 | 11/13/2008 | 11/13/2008 | A | NR |
Forrest France
|
|
|
Underground fire department connection pipe flush postponed until repairs are made.
|
INSP-Sprinkler Rough-in/Hydro | 11/12/2008 | 11/13/2008 | 11/13/2008 | A | FAIL |
Forrest France
|
|
|
Hydrostatic testing for the remote FDC UG piping failed due to significant pressure loss at the guage.
|
INSP-Sprinkler Rough-in | 11/5/2008 | 11/5/2008 | 11/5/2008 | P | PART |
Forrest France
|
|
|
Remote FDC UG piping okayed for cover per resubmittals.
|
INSP-Sprinkler Rough-in/Hydro | 11/3/2008 | 11/4/2008 | 11/4/2008 | A | NR |
Forrest France
|
|
|
See inspection comments completed 10/6/08.
|
INSP-Sprinkler Rough-in/Hydro | 10/6/2008 | 10/6/2008 | 10/6/2008 | A | FAIL |
Forrest France
|
|
|
Inspection for the 1st floor failed due to field changes in pipe routing, head locations and floor plan layout in difference to the stamped approved plan set. Will need to provide accurate resubmittals for on site inspection prior to approval for ceiling cover.
|
INSP-Sprinkler Rough-in/Hydro | 7/11/2008 | 7/14/2008 | 7/15/2008 | A | PART |
Forrest France
|
|
|
OH hydrostatic testing for the dry system passed, still need to complete 24 hr. air testing. Rough-in inspection for the parking garage levels PA 1, 2, 3, 4, and the storage areas also completed-see annotations on plan for defficiencies including spacing, head locations, head temp, etc.
|
FIR-Aging Inspection | 6/19/2008 | 6/19/2008 | 6/19/2008 | | DONE |
Forrest France
|
|
|
Work in progress, construction underway.
|