INSP-Final Inspection | 12/9/2008 | 12/11/2008 | 12/11/2008 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 12/8/2008 | 12/9/2008 | 12/9/2008 | P | FAIL |
Troy Cobbley
|
|
|
All of the smoke detectors and manual pull stations have been tested including phone line troubles and battery tourbles. Phone line one appears to have a problem. Audio/visuals need to be tested as well as end of line voltage. A map at the facp is required.
|
INSP-Final Inspection | 12/5/2008 | 12/8/2008 | 12/8/2008 | P | FAIL |
Troy Cobbley
|
|
|
This inspection turned into a first floor walk through/conference. All of the first floor wing smoke detectors are overspaced, a smoke detector in the common are needs to be relocated closer to the double doors to the wing and visuals are overspaced. Locations are marked on the plans. No testing was performed.
|
FIR-Aging Inspection | 11/24/2008 | 11/24/2008 | 11/26/2008 | | NR |
Troy Cobbley
|
|
|
Per Darcy the work for this project is in progress.
|