INSP-Final Inspection | 7/22/2008 | 7/22/2008 | 7/22/2008 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled.
|
INSP-Final Inspection | 7/18/2008 | 7/18/2008 | 7/18/2008 | P | FAIL |
Troy Cobbley
|
|
|
Provide locks and/or chains for both of the PIV's and I need verification that the intake pipe in the new storage tank is at the correct height.
|
INSP-Sprinkler Rough-in/Hydro | 7/16/2008 | 7/17/2008 | 7/17/2008 | P | PASS |
Troy Cobbley
|
|
|
The underground hydro test passed and the underground flush passed.
|
INSP-Sprinkler Rough-in/Hydro | 5/7/2008 | 5/8/2008 | 5/8/2008 | A | PASS |
Troy Cobbley
|
|
|
24 hour air test passed
|
INSP-Sprinkler Rough-in/Hydro | 5/6/2008 | 5/7/2008 | 5/7/2008 | A | PART |
Troy Cobbley
|
|
|
24 hour air test started at 8:30am with 45 psi on the guage.
|
INSP-Sprinkler Rough-in/Hydro | 5/2/2008 | 5/6/2008 | 5/6/2008 | A | PASS |
Troy Cobbley
|
|
|
Above ground hydro test passed.
|
INSP-Sprinkler Rough-in/Hydro | 5/1/2008 | 5/2/2008 | 5/2/2008 | P | FAIL |
Troy Cobbley
|
|
|
Above ground hydro test failed due to leaks. To be rescheduled for monday.
|
INSP-Sprinkler Rough-in | 4/3/2008 | 4/4/2008 | 4/4/2008 | P | PASS |
Troy Cobbley
|
|
|
The remaining underground piping is ok to cover.
|