INSP-Final Inspection | 3/9/2009 | 3/9/2009 | 3/9/2009 | P | PASS |
Forrest France
|
|
|
Corrections completed, fire sprinkler permit finaled.
|
INSP-Final Inspection | 2/5/2009 | 2/6/2009 | 2/6/2009 | A | NH |
Forrest France
|
|
|
Ryan is the contact. Thanks Phone #: ###-#### Internet Inspection Request from: Stan Beus
|
INSP-Final Inspection | 2/4/2009 | 2/5/2009 | 2/5/2009 | A | PART |
Forrest France
|
|
|
Need as-built plans prior to permit final.
|
INSP-Final Inspection | 1/9/2009 | 1/12/2009 | 1/12/2009 | P | FAIL |
Forrest France
|
|
|
Four missing escutcheons, basement level storage room 001 has not been sprinklered.
|
INSP-Sprinkler Rough-in/Hydro | 12/5/2008 | 12/5/2008 | 12/5/2008 | P | PART |
Forrest France
|
|
|
Rough-in okayed for cover.
|
INSP-Sprinkler Rough-in | 10/16/2008 | 10/17/2008 | 10/17/2008 | P | PART |
Forrest France
|
|
|
Previous c/n items for the overhead rough-in have been corrected, install is okay for cover when main tie-ins have been finished.
|
INSP-Sprinkler Rough-in/Hydro | 10/16/2008 | 10/16/2008 | 10/16/2008 | A | PART |
Forrest France
|
|
|
Hydrostatic test for the wet and antifreeze systems east remodel area syst. #2 completed acceptable.
|
INSP-Sprinkler Rough-in/Hydro | 10/14/2008 | 10/15/2008 | 10/16/2008 | P | FAIL |
Forrest France
|
|
|
Need to add coverage at one closet and adjust spacing at one location in the attic-see plans for annotations.
|
INSP-Final Inspection | 5/27/2008 | 5/27/2008 | 5/27/2008 | P | NR |
Forrest France
|
|
|
Permit work is not yet completed for final approval, system riser #2 feeding the east remodel is not in service as rough-in is not finished, riser #1 supervisory and alarm system interconnection tested okay-fire sprinkler install for work completed to date for "phase 1" appears acceptable.
|
INSP-Final Inspection | 5/22/2008 | 5/23/2008 | 5/23/2008 | A | CANC |
Forrest France
|
|
|
Mike B is the contact. Thanks Phone #: ###-#### Internet Inspection Request from: Stan Beus Overbooked, inspection rescheduled per phone call to contractor.
|
INSP-Sprinkler Rough-in/Hydro | 4/3/2008 | 4/4/2008 | 4/4/2008 | A | DONE |
Forrest France
|
|
|
Overhead hydro completed, passed.KR
|
INSP-Sprinkler Rough-in | 3/28/2008 | 3/31/2008 | 3/31/2008 | A | DONE |
Forrest France
|
|
|
OK to cover in mens and womans restrooms.Changes complete per Forrest last inspection. KR
|
INSP-Sprinkler Rough-in | 3/26/2008 | 3/27/2008 | 3/27/2008 | A | FAIL |
Forrest France
|
|
|
One upright head at the womens restroom is blocked by adjacent ductwork, one ssu at the mens restroom is obstructed by the top joist cord which extends below and directly next to the deflector, missing EQ brace at the last piece of main. Areas approved for cover include the hall 116, sacristy 115, and the narthex entry 101-see stamped plans for initialed locations. Also verified resubmittals match installation at areas where field modifications were done.
|
INSP-Sprinkler Rough-in/Hydro | 3/3/2008 | 3/4/2008 | 3/4/2008 | A | FAIL |
Forrest France
|
|
|
Provide plan resubmittals reflecting field modifications and installation of CPVC piping for several branchlines.
|