Information based on query as of Friday, July 5, 2024.
Permit Information
Permit NumberFIR08-00045
StatusFinaled
Name WESTERN STATES FIRE PROTECTION
Site Address 512 N 8TH ST
Project NameST. MICHAEL'S
Customer Number 
ePlanReview 
Description
11/13/08 Revised FIR Scope of Work:
These plans were submitted as an As-Built of the project Scope of Work:
(ST. MICHAEL'S EPISCOPAL CHURCH - BISHOP TUTTLE HOUSE AND SITE WORK - PHASE I) The Bishop Tuttle House and the Funsten House will be fire sprinklered for story increase and for code trade-offs. To remodel the 3,424 square foot basement and 3,616 square foot 1st story of the Bishop Tuttle House of St. Michael's Episcopal Church. A 950 square foot 1st story mezzanine addition will also be constructed. The Bishop Tuttle House and the Funsten house will be fully fire sprinklered in conjunction with this permit. The work is required to comply with the approved drawings, with the plan review report, and with all applicable codes. The fire sprinkler system is required to comply with NFPA 13 as regulated by the Fire Department. The combination of parcels must be completed before this permit is given a final. The fire sprinkler system work shall comply with the IFC 2006, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to building permit: BLD07-01784. This permit is not attached to any other permit.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection10/2/200910/5/200910/5/2009APASS
DetailsForrest France
Fire sprinkler permit approved for final status.
INSP-Final Inspection9/14/20099/14/20099/15/2009PNR
DetailsForrest France
Work incompleted on correction notice items.
INSP-Final Inspection8/12/20098/14/20098/14/2009AFAIL
DetailsForrest France
See stamped plan set for locations in need or revision including overspaced heads at the kitchen 103, one overspaced head at the basement hallway, one blocked upright at a closet 1st floor, need to provide access to three locked rooms and the elevator pit, one sw head at the stairway needs the travel cap removed, escutcheons missing at three heads.
INSP-Sprinkler Rough-in/Hydro2/23/20092/23/20092/23/2009PPASS
DetailsTroy Cobbley
Hydro Test Passed for wet and AnitFreeze
INSP-Sprinkler Rough-in/Hydro2/20/20092/23/20092/23/2009AFAIL
DetailsTroy Cobbley
Hydro test was not even started due to the fitter finding a leak.
INSP-Final Inspection2/19/20092/19/20092/19/2009PNR
DetailsForrest France
casey - please call 1/2 hr prior Phone #: ###-####
INSP-Sprinkler Rough-in/Hydro1/21/20091/22/20091/22/2009PPART
DetailsForrest France
Verified resubmitted plans for installation changes at the 1st floor area funsten house, okay for ceiling cover as initialed and annotated with today's date, noted flex couplings to be provided at the floor penetration for the 4" main.
INSP-Sprinkler Rough-in8/29/20088/29/20088/29/2008PFAIL
DetailsForrest France
On site visit to confirm notes per last inspection completed 8/19. Dry upright sprinkler coverage is overspaced or missing at several locations, noted several field modifications which will necessitate resubmitted plans matching the installation.
INSP-Sprinkler Rough-in8/28/20088/28/20088/28/2008PFAIL
DetailsForrest France
Chris- call 30 min prior to going to meet Phone #: ###-#### No access yet provided to inspect dry uprights as noted per last site visit completed 8/19, inspection rescheduled per phone conversation.
INSP-Sprinkler Rough-in/Hydro8/18/20088/19/20088/19/2008AFAIL
DetailsTroy Cobbley
Resubmittals are needed showing the upright heads being changed to pendant heads, added upright heads in the daycare/remote area, and all of the added pendants in the closets. The entire space above the ceiling, in the daycare, will need to be covered with sprinklers or a code based solution provided. Access shall be provided to view the dry upright sprinkler heads. The uprights have been deleted from the corridors but there is exposed wood above the ceilings in the corridors. Reducing fittings have been used and are not allowed per NFPA 13 unless the exception is met.
INSP-Sprinkler Rough-in/Hydro6/12/20086/12/20086/12/2008PNR
DetailsForrest France
Jerry Phone#: ###-####
INSP-Sprinkler Rough-in5/30/20085/30/20085/30/2008PPART
DetailsTroy Cobbley
This inspection was for the installation of the 4" PIV. The PIV can be covered. I let the contractor know that it would be a good idea to get the conduit for the tamper switch installed prior to bury.
INSP-Sprinkler Rough-in/Hydro5/12/20085/13/20085/13/2008AFAIL
DetailsForrest France
See approved plan set for attic area clouded per inspection completed today-noted one hanger at the 4" main to be reattatched, one missing hanger, and one upright head blocked by and adjacent truss web.
INSP-Sprinkler Rough-in5/12/20085/12/20085/12/2008PNR
DetailsForrest France
jerry Phone #: ###-####
INSP-Sprinkler Rough-in5/1/20085/1/20085/5/2008PPART
DetailsForrest France
OH fire sprinkler okayed for cover at the hard lid intermediate landing adjacent to the east stairway.
INSP-Sprinkler Rough-in4/15/20084/15/20084/16/2008PPART
DetailsForrest France
See approved plans for hard lid restroom areas at the basement okayed for cover.
INSP-Sprinkler Rough-in4/3/20084/4/20084/4/2008APART
DetailsForrest France
Ok to cover main entance of Bishop tuttle house room# 109 stairwell.KR
INSP-Conference4/1/20084/1/20084/1/2008PDONE
DetailsTroy Cobbley
Jerry wanted to know precedures for getting some of the sprinkler piping covered. I notified him we could do partial rough-in sprinkler inspections.