INSP-Final Inspection | 4/24/2008 | 4/25/2008 | 4/25/2008 | A | PASS |
Forrest France
|
|
|
Noted corrections are complete, fire sprinkler work passed inspection, permit finaled.
|
INSP-Sprinkler Rough-in | 4/7/2008 | 4/7/2008 | 4/7/2008 | P | PART |
Forrest France
|
|
|
All corrections made per Forrest notes.OK to cover all areas except the reception desk at the southeast office.See redline on city approved plans.KR
|
INSP-Sprinkler Rough-in | 3/21/2008 | 3/24/2008 | 3/24/2008 | A | FAIL |
Forrest France
|
|
|
Heads at two areas are overspaced including the vestibule and one storage room-see plans for locations, also need to plug the outlet used for an auxillary drain above the ceiling, heads at the room marked "file storage" are overspaced per room usage-verify use or provide coverage per plan.
|
INSP-Sprinkler Rough-in | 3/5/2008 | 3/5/2008 | 3/5/2008 | P | PART |
Forrest France
|
|
|
See approved plans for areas initialed with today's date okayed for cover at the hard lid ceilings for the east remodel area.
|
INSP-Sprinkler Rough-in | 2/21/2008 | 2/21/2008 | 2/21/2008 | P | PART |
Forrest France
|
|
|
Ok to cover electrical room, see red lined notes on approved city plans. KR
|