INSP-Final Inspection | 12/23/2008 | 12/24/2008 | 12/24/2008 | A | PASS |
Forrest France
|
|
|
UG fire supply line permit finaled.
|
INSP-Final Inspection | 12/22/2008 | 12/23/2008 | 12/23/2008 | P | CANC |
Forrest France
|
|
|
Please coordinate with alarm star Phone #: ###-#### Internet Inspection Request from: Trent Bice Inspection cancelled from web by: Trent Bice
|
INSP-Sprinkler Rough-in/Hydro | 8/14/2008 | 8/14/2008 | 8/15/2008 | P | PASS |
Troy Cobbley
|
|
|
Aboveground and Under ground Hydro tests passed.
|
INSP-Sprinkler Rough-in/Hydro | 8/13/2008 | 8/14/2008 | 8/14/2008 | A | FAIL |
Troy Cobbley
|
|
|
No access to the riser room. No one on the job site.
|
INSP-Sprinkler Rough-in | 6/4/2008 | 6/5/2008 | 6/5/2008 | A | PART |
Troy Cobbley
|
|
|
The lateral earthquake bracing is overspaced. The branchline piping sizing below the mezzanine does not match the approved drawings. This area is a remote area. Resubmitt plans showing the pipe size revisions and revised hydraulic calculations.
|
INSP-Supply line flush | 4/10/2008 | 4/11/2008 | 4/11/2008 | P | PASS |
Troy Cobbley
|
|
|
UG flush passed
|
INSP-Sprinkler Rough-in | 2/19/2008 | 2/20/2008 | 2/20/2008 | P | PASS |
Troy Cobbley
|
|
|
Underground supply piping is ok to cover
|