Information based on query as of Thursday, July 18, 2024.
Permit Information
Permit NumberFIR08-00188
StatusFinaled
Name DEBEST FIRE PROTECTION
Site Address 2854 S FEATHERLY WAY
Project NameSystem Tech INC
Customer Number 
ePlanReview 
Description
Work Scope: OH Scope: Beginning from an existing supply 6” supply located within a 1 hour rated riser room at the North East corner of the bldg. install a 6” wet riser and wet pipe grid system to serve through out the entire bldg. The system is designed to Ordinary Group II for Mezzanine area, Light Hazard through out the office area and designed to protect Class I – IV commodity up to 16’ in a palletized solid pile, bin box or shelf storage arrangement through out the warehouse.
The fire sprinkler system work shall comply with the IFC 2006, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to BLD07-02854. The underground was previously approved under separate permit # FIR08-00148.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection10/15/200810/15/200810/15/2008PPASS
DetailsTroy Cobbley
Fire sprinkler permit finaled.KR
INSP-Final Inspection10/13/200810/14/200810/14/2008PCANC
DetailsTroy Cobbley
Final Inspection - Contact: Todd Phone #: ###-#### x1234 Internet Inspection Request from: Alicia Pauley
INSP-Sprinkler Rough-in/Hydro9/10/20089/11/20089/11/2008APASS
DetailsTroy Cobbley
Forward Flow Test passed
INSP-Sprinkler Rough-in/Hydro9/5/20089/8/20089/8/2008APASS
DetailsTroy Cobbley
The remaining sprinkler piping above the lay-in ceilings can be covered.
INSP-Supply line flush8/5/20088/5/20088/5/2008PPASS
DetailsTroy Cobbley
OH Hydro Passed
INSP-Sprinkler Rough-in/Hydro8/4/20088/4/20088/4/2008PPASS
DetailsTroy Cobbley
See the approved plans for locations where the sprinkler piping above the hard lids can be covered.
INSP-Sprinkler Rough-in7/17/20087/18/20087/18/2008PPASS
DetailsTroy Cobbley
The overhead rough-in inspection passed.
FIR-Aging Inspection6/26/20086/26/20086/26/2008 DONE
DetailsForrest France
Site visit confirmed construction underway, work in progress.