INSP-Final Inspection | 9/15/2008 | 9/17/2008 | 9/17/2008 | A | PASS |
Troy Cobbley
|
|
|
Testing for pre-action system completed. Tested interconnection to fire alarm panel also performed a foward flush. KR
|
INSP-Final Inspection | 9/10/2008 | 9/12/2008 | 9/12/2008 | A | CANC |
Troy Cobbley
|
|
|
Phone #: ###-#### Internet Inspection Request from: bruce stricker
|
INSP-Sprinkler Rough-in/Hydro | 6/25/2008 | 6/26/2008 | 6/26/2008 | P | DONE |
Forrest France
|
|
|
Hydro test complete. KR
|
INSP-Sprinkler Rough-in/Hydro | 6/17/2008 | 6/18/2008 | 6/18/2008 | A | PART |
Troy Cobbley
|
|
|
The 24 hour air test passed. The rough-in inspection passed. Two hangers in the west corridor need to be removed from the truss bracing and a missing hanger needs to be installed on the 2" branchline as discussed. Piping can be covered. Some sprinkler heads are overspaced as per the hydraulic calculations but the minumum gpm/psi required for the remote area exceeds the gpm/psi required for the larger square footage of the heads. I spoke to Brian about this issue as well. Piping can be covered. I spoke to the fire sprinkler contractor about the requirement for the forward flush and a 200lb hydro test.
|
INSP-Sprinkler Rough-in/Hydro | 6/16/2008 | 6/17/2008 | 6/17/2008 | P | PART |
Troy Cobbley
|
|
|
The 24 hour air test was started at 9:45 with just over 40psi on the guage.
|