Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberFIR08-00203
StatusFinaled
Name CONSOLIDATED FIRE TECH
Site Address 10215 W EMERALD ST
Project NameFIBER PIPE INC
Customer Number 
ePlanReview 
Description
overhead Scope of Work: OH Only
An existing preaction system which serves the upright protection above the data room will be modified by removing the upright protection and plugging the outlets. The existing branchlines which serve other areas will remain. A new 4” double interlock preaction riser and piping will be installed to serve pendant heads located below an existing ceiling in the data room. All work shall comply with NFPA 13-2007 & the IFC-2006, attached review comment and conditions list, as regulated by the Fire Chief. These notes, permit and fire “Inspection Card” are required to be on site as a condition of this work, to provide witness of compliance verification of minimum fire code. This permit is not attached to any other permit:
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection9/15/20089/17/20089/17/2008APASS
DetailsTroy Cobbley
Testing for pre-action system completed. Tested interconnection to fire alarm panel also performed a foward flush. KR
INSP-Final Inspection9/10/20089/12/20089/12/2008ACANC
DetailsTroy Cobbley
Phone #: ###-#### Internet Inspection Request from: bruce stricker
INSP-Sprinkler Rough-in/Hydro6/25/20086/26/20086/26/2008PDONE
DetailsForrest France
Hydro test complete. KR
INSP-Sprinkler Rough-in/Hydro6/17/20086/18/20086/18/2008APART
DetailsTroy Cobbley
The 24 hour air test passed. The rough-in inspection passed. Two hangers in the west corridor need to be removed from the truss bracing and a missing hanger needs to be installed on the 2" branchline as discussed. Piping can be covered. Some sprinkler heads are overspaced as per the hydraulic calculations but the minumum gpm/psi required for the remote area exceeds the gpm/psi required for the larger square footage of the heads. I spoke to Brian about this issue as well. Piping can be covered. I spoke to the fire sprinkler contractor about the requirement for the forward flush and a 200lb hydro test.
INSP-Sprinkler Rough-in/Hydro6/16/20086/17/20086/17/2008PPART
DetailsTroy Cobbley
The 24 hour air test was started at 9:45 with just over 40psi on the guage.