Permit NumberFIR08-00214
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 7107 W FAIRVIEW AVE
Project NameNORTHWEST ANIMAL HOSPITAL
Customer Number 
ePlanReview 
Description
Work Scope: OH Only - Northwest Animal Hospital - To construct a new 8,660 square foot, one story, masonry wall and framed animal hospital and kennel building and related site improvements. The animal hospital area is 5,380 square feet and the grooming, training and dog kennel areas are 3,280 square feet. All construction per the approved plans and attached comment list.
OH Scope: Beginning from an existing supply and an 6” x 4” flange located at the Northwest corner of the bldg., install a 4” wet riser and wet pipe system to serve through out the entire bldg. The system supply will be controlled fro a Wall Post Indicating valve located at the riser. The system criteria is designed to Light Hazard.
The fire sprinkler system work shall comply with the IFC 2006, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to BLD06-02489 & UG permit FIR07-01027.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection8/5/20088/7/20088/7/2008PPASS
DetailsForrest France
OH fire sprinkler permit finaled, notified contractor to request project related UG supply permit for final.
INSP-Sprinkler Rough-in/Hydro7/14/20087/14/20087/14/2008PPASS
DetailsTroy Cobbley
hydro of fdc passed
INSP-Sprinkler Rough-in/Hydro7/11/20087/11/20087/11/2008PPART
DetailsTroy Cobbley
The overhead hydro passed but the FDC was not included in the test as required per NFPA13.
INSP-Sprinkler Rough-in/Hydro7/2/20087/3/20087/3/2008AFAIL
DetailsForrest France
Hydro test failed gauge dropped 4 psi. Overhead OK to cover. KR
INSP-Conference5/21/20085/22/20085/22/2008ADONE
DetailsTroy Cobbley
The high area sprinkler piping can now be covered.
INSP-Sprinkler Rough-in/Hydro5/7/20085/8/20085/8/2008PPASS
DetailsTroy Cobbley
The upper level piping rough-in is passed.
INSP-Sprinkler Rough-in/Hydro5/6/20085/7/20085/7/2008PPART
DetailsTroy Cobbley
The sprinkler rough-in for piping in the low areas is passed. The high area was not quite complete. The sprinkler piping can not be covered until the deck mounted insulation has been installed. I notified the fitter and the general contractor about a potential problem with the eaves qualifying as a combustible concealed space requireing protection.