INSP-Final Inspection | 8/5/2008 | 8/7/2008 | 8/7/2008 | P | PASS |
Forrest France
|
|
|
OH fire sprinkler permit finaled, notified contractor to request project related UG supply permit for final.
|
INSP-Sprinkler Rough-in/Hydro | 7/14/2008 | 7/14/2008 | 7/14/2008 | P | PASS |
Troy Cobbley
|
|
|
hydro of fdc passed
|
INSP-Sprinkler Rough-in/Hydro | 7/11/2008 | 7/11/2008 | 7/11/2008 | P | PART |
Troy Cobbley
|
|
|
The overhead hydro passed but the FDC was not included in the test as required per NFPA13.
|
INSP-Sprinkler Rough-in/Hydro | 7/2/2008 | 7/3/2008 | 7/3/2008 | A | FAIL |
Forrest France
|
|
|
Hydro test failed gauge dropped 4 psi. Overhead OK to cover. KR
|
INSP-Conference | 5/21/2008 | 5/22/2008 | 5/22/2008 | A | DONE |
Troy Cobbley
|
|
|
The high area sprinkler piping can now be covered.
|
INSP-Sprinkler Rough-in/Hydro | 5/7/2008 | 5/8/2008 | 5/8/2008 | P | PASS |
Troy Cobbley
|
|
|
The upper level piping rough-in is passed.
|
INSP-Sprinkler Rough-in/Hydro | 5/6/2008 | 5/7/2008 | 5/7/2008 | P | PART |
Troy Cobbley
|
|
|
The sprinkler rough-in for piping in the low areas is passed. The high area was not quite complete. The sprinkler piping can not be covered until the deck mounted insulation has been installed. I notified the fitter and the general contractor about a potential problem with the eaves qualifying as a combustible concealed space requireing protection.
|