INSP-Final Inspection | 4/15/2009 | 4/15/2009 | 4/15/2009 | P | PASS |
Forrest France
|
|
|
Fire alarm permit finaled.
|
INSP-Final Inspection | 10/22/2008 | 10/24/2008 | 10/24/2008 | P | PART |
Forrest France
|
|
|
All corrections were made. Fire alarm testing complete. Can not final until we have copys of NFPA 72 and map at anunciator. KR
|
INSP-Final Inspection | 10/14/2008 | 10/14/2008 | 10/14/2008 | P | PART |
Forrest France
|
|
|
One fire damper in up stairs storage area behind stage was not connected to fire alarm system, a module will be added to smoke detectors. All fire alarm testing completed in assembly area except as noted above. NFPA inspection report must be completed before complete final. KR
|
INSP-Final Inspection | 10/9/2008 | 10/13/2008 | 10/13/2008 | A | FAIL |
Forrest France
|
|
|
See red lined notes on plans at area A for locations in need of revision including horn and speaker/strobe devices.
|
INSP-Final Inspection | 8/11/2008 | 8/15/2008 | 8/15/2008 | A | PART |
Forrest France
|
|
|
See notice of violation paper work for corrections completed.KR
|
INSP-Alarm Testing | 8/11/2008 | 8/11/2008 | 8/12/2008 | A | PART |
Forrest France
|
|
|
Fire dampers passed testing with the exception of one damper at corridor B01-see plans for location, some items on c/n repaired. Items remaining include EOL voltage testing, provide list of signals recieved, area "A" auditorium is not complete including voice evac., two elevators are not finished, kitchen hood interconnect needs tested, noted two supervisory signals at the FACP due to elevator power loss, need to test nac batteries, provide NFPA 72 Record of Completion documents at final inspection.
|
INSP-Final Inspection | 8/6/2008 | 8/8/2008 | 8/8/2008 | A | PART |
Forrest France
|
|
|
Refer to red-lines on approved plan set for noted deficiencies and remainder of work to be completed and inspected.
|
INSP-Final Inspection | 8/6/2008 | 8/6/2008 | 8/6/2008 | P | FAIL |
Forrest France
|
|
|
See red line notes on plans for deficiencies and areas tested today per site visit by K. Roule.
|
INSP-Final Inspection | 7/31/2008 | 8/5/2008 | 8/5/2008 | A | PART |
Forrest France
|
|
|
See red line notes on approved plan set for continuation of initiation devices tested today and locations in need of correction.
|
INSP-Final Inspection | 7/31/2008 | 8/4/2008 | 8/4/2008 | A | PART |
Forrest France
|
|
|
See red-lines on plans for locations of initiation devices tested today and areas in need of adjustment.
|
INSP-Final Inspection | 7/29/2008 | 8/1/2008 | 8/1/2008 | A | PART |
Forrest France
|
|
|
Manual pull stations and notification devices tested today per K. Roule, see plans for locations in need of adjustment.
|
INSP-Final Inspection | 7/30/2008 | 7/31/2008 | 7/31/2008 | A | FAIL |
Forrest France
|
|
|
Walkthrough of classroom wings areas J,I, E and F completed today- noted items on plans in need of correction including smoke detectors to be relocated due to proximity to HVAC registers, spacing or cd adjustment at some av's, pull stations at two locations, noted minor floor plan changes, initiation devices not tested due to missing phone lines.
|
INSP-Final Inspection | 3/27/2009 | 3/27/2009 | | P | |
Forrest France
|
|
|
Contact Rafe Phone#: ###-####
|