INSP-Final Inspection | 7/7/2009 | 7/8/2009 | 7/8/2009 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 6/29/2009 | 6/30/2009 | 6/30/2009 | A | FAIL |
Troy Cobbley
|
|
|
The devices at the new riser at the east side of the building functioned correctly. The new devices in the elevator did not function correctly. An inspection will need to be resceduled with the elevator contractor.
|
INSP-Alarm Testing | 3/2/2009 | 3/3/2009 | 3/3/2009 | P | PASS |
Troy Cobbley
|
|
|
The fire alarm for the Corrections area is now complete.
|
INSP-Alarm Testing | 2/26/2009 | 2/26/2009 | 2/27/2009 | P | FAIL |
Troy Cobbley
|
|
|
This inspection was for the Corrections tenant expansion into the new area of the first floor. NAC circuit #4 did not meet the minimum 21.6 volt requirement at the end of line. Caps were missing from the end of the sample tubes for the two duct smoke detectors tested. There have been significant changes to the notification circuits and resubmittals will be required prior to a final inspection and sign off.
|
FIR-Aging Inspection | 8/4/2008 | 8/4/2008 | 8/4/2008 | | NR |
Troy Cobbley
|
|
|
work is in progress
|