INSP-Final Inspection | 8/21/2008 | 8/22/2008 | 8/22/2008 | A | PASS |
Forrest France
|
|
|
Noted corrections are complete, plans verified, fire sprinkler permit finaled.
|
INSP-Final Inspection | 8/20/2008 | 8/21/2008 | 8/21/2008 | P | CANC |
Forrest France
|
|
|
|
INSP-Sprinkler Rough-in/Hydro | 7/8/2008 | 7/8/2008 | 7/8/2008 | P | FAIL |
Forrest France
|
|
|
Completed only a preliminary field inspection as contractor did not provide approved plans, review notes, inspection record/permit card on site as required per condition of the permit for verification of compliance, missing branch line hangers at several locations, need to provide sealant at all penetrations by sprinkler drops at the cooler enclosure, two DP are not yet installed, rough-in install cannot be okayed until stamped plans and associated documents are provided.
|