INSP-Final Inspection | 2/3/2009 | 2/3/2009 | 2/3/2009 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled. A tree was removed from infront of the strobe in the employee breakroom.
|
INSP-Alarm Testing | 12/24/2008 | 12/31/2008 | 12/31/2008 | A | CANC |
Troy Cobbley
|
|
|
mark Phone #: ###-####
|
INSP-Alarm Testing | 12/24/2008 | 12/30/2008 | 12/30/2008 | A | CANC |
Troy Cobbley
|
|
|
mark Phone #: ###-####
|
INSP-Alarm Testing | 12/24/2008 | 12/29/2008 | 12/29/2008 | A | FAIL |
Troy Cobbley
|
|
|
Need the north red alarm strobe repaired and tested, the new duct smoke detector does not shut down the hvac unit and the fire alarm system needs to be finished in the existing east rooms.
|
INSP-Final Inspection | 12/23/2008 | 12/24/2008 | 12/24/2008 | A | PART |
Forrest France
|
|
|
Alarm and supervisory conditions for both the new sprinkler risers and the two existing risers tested today, functionality testing passed for all four preaction systems, noted the wall mounted PIV for the new west riser is not adjusted correctly to activate within 1/5 of valve closure, also discovered the outside bell at the existing riser is not operational. Discussed SD locations at beam pockets in the corridor and mounting heights of existing pull stations at the east side of the building.
|
INSP-Alarm Testing | 12/16/2008 | 12/18/2008 | 12/18/2008 | A | FAIL |
Troy Cobbley
|
|
|
No inspection was performed today but a correction notice was left with Mark. The correction notice lists: Provide resubmittals showing the door mag/locks and test the interconnection with the fire alarm panel, the two amber strobes inside of and the two red strobes outside of the large preaction room are the incorrect candella as per the plans, all of the alarm interconnections with the existing and new preaction sprinkler systems need to be tested, the graphic annunciator is non-functional and needs to be tested/repaired, the alarm system for the large preaction room needs tested, the facp needs to be re-programmed to operate the preaction valves per review comment #3, provide tests reports reflecting the devices already tested as marked on the resubmitted plans and provide a completed/installed fire alarm system that is fully functional with a clear panel as per IFC 907.18.
|
INSP-Alarm Testing | 12/16/2008 | 12/17/2008 | 12/17/2008 | A | DONE |
Troy Cobbley
|
|
|
Additional initiating devices were tested today. See the city approved plans for devices. The fire alarm plans need to be resubmitted showing the door magnets. Also the fire alarm panel is having undefined troubles showing up and the graphic annunciator is not operating. No more testing will be done until the fire alarm system is completely functional.
|
INSP-Alarm Testing | 12/15/2008 | 12/16/2008 | 12/16/2008 | A | DONE |
Troy Cobbley
|
|
|
See the city approved plans for devices tested. The audio/visuals were also tested. The interconnections between the NAC panels tested ok. The existing NAC panel in the mechanical room needs 12.7 ah batteries. Supervision failed on the 110ah battery backup.
|
FIR-Aging Inspection | 8/15/2008 | 8/15/2008 | 8/15/2008 | | NR |
Troy Cobbley
|
|
|
Work is in progress
|