INSP-Final Inspection | 10/16/2008 | 10/17/2008 | 10/17/2008 | A | PASS |
Forrest France
|
|
|
Correction notice items verified for completion, fire sprinkler permit finaled.
|
INSP-Final Inspection | 10/13/2008 | 10/14/2008 | 10/14/2008 | A | FAIL |
Forrest France
|
|
|
Inspection failed due to several items including one painted head at the electrical room, leaking pendent at the pharmacy area, dry pendent heads are not yet installed at the coolers, missing escutcheon at the staff restroom, provide correct pipe hanger at the outside storage locker, need as-builts for field mods, PIV tamper is not correcly adjusted, waterflow switch needs adjustment, provide pitot guage for forward flow testing, need main control signage at the riser #1 and #2 shutoff valves.
|
INSP-Sprinkler Rough-in/Hydro | 9/18/2008 | 9/19/2008 | 9/19/2008 | A | PART |
Forrest France
|
|
|
OH hydrostatic testing including the wet and antifreeze loop system passed, verified c/n items, noted concealed heads at the restrooms may be obstructed by adjacent surface mounted light fixtures when installed.
|
INSP-Sprinkler Rough-in | 8/22/2008 | 8/25/2008 | 8/25/2008 | A | FAIL |
Forrest France
|
|
|
SW heads at the sign tower antifreeze loop are overspaced and below max. listed distance from the ceiling, noted several missing retaining straps at numerous locations including mains and branch lines-somel installed while on site, combustibles above the restrooms must be removed or protection provided, waiting area drops are 3/4"-plan shows 1/2" heads, four upright heads at the stock room are obstructed by beams or exceed min. spacing.
|