INSP-Final Inspection | 8/21/2008 | 8/22/2008 | 8/22/2008 | P | PASS |
Forrest France
|
|
|
Drop ceilings installed, fire sprinkler permit finaled.
|
INSP-Final Inspection | 8/14/2008 | 8/15/2008 | 8/15/2008 | P | PART |
Forrest France
|
|
|
Permit final pending completion of work at the basement level new fabrication room as red-lined on plans.
|
INSP-Final Inspection | 8/13/2008 | 8/14/2008 | 8/14/2008 | P | NR |
Forrest France
|
|
|
Project is not ready for final per conversation with general contractor, inspection to be scheduled 8/15.
|
INSP-Sprinkler Rough-in | 7/29/2008 | 7/29/2008 | 7/29/2008 | P | PART |
Forrest France
|
|
|
Resubmittal drawings accepted, rough-in install is approved for cover.
|