INSP-Final Inspection | 10/13/2008 | 10/14/2008 | 10/14/2008 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 10/13/2008 | 10/13/2008 | 10/13/2008 | P | FAIL |
Troy Cobbley
|
|
|
The project is not ready for a final yet.
|
INSP-Sprinkler Rough-in/Hydro | 10/10/2008 | 10/13/2008 | 10/13/2008 | A | PASS |
Troy Cobbley
|
|
|
The overhead hydro, underground hydros & fdc flush passed
|
INSP-Sprinkler Rough-in/Hydro | 10/8/2008 | 10/9/2008 | 10/9/2008 | P | CANC |
Troy Cobbley
|
|
|
Note: FDC Flush Phone #: ###-####.
|
INSP-Sprinkler Rough-in/Hydro | 10/6/2008 | 10/7/2008 | 10/7/2008 | A | DONE |
Troy Cobbley
|
|
|
Under ground flush completed. KR
|
INSP-Sprinkler Rough-in | 10/6/2008 | 10/7/2008 | 10/7/2008 | A | DONE |
Troy Cobbley
|
|
|
Remaining areas per Troys last inspection can be covered.KR
|
INSP-Sprinkler Rough-in | 9/29/2008 | 9/30/2008 | 9/30/2008 | A | PASS |
Troy Cobbley
|
|
|
The underground piping for the remote FDC and the hose station can be covered except for both ends since thrust blocks, drains and vaults had not been installed yet. As-built plans need to be submitted showing the the positions of the two lines being switched and the remote hose station being relocated to the south.
|
INSP-Sprinkler Rough-in/Hydro | 9/24/2008 | 9/24/2008 | 9/24/2008 | P | PASS |
Troy Cobbley
|
|
|
The underground hydro test passed.
|
INSP-Sprinkler Rough-in | 9/15/2008 | 9/15/2008 | 9/15/2008 | P | PASS |
Troy Cobbley
|
|
|
The piping in the mezzanine can be covered. An as-built has been provided showing the extension of the mezzanine and the additional sprinkler protection.
|
INSP-Sprinkler Rough-in/Hydro | 8/25/2008 | 8/25/2008 | 8/25/2008 | P | PART |
Forrest France
|
|
|
OH inspection for the court area mains and branchlines only completed today-the lower mezzanine piping is not yet installed, noted one missing EQ brace at the NW corner-location circled on plans, noted high temp. heads in place at the vicinity of the unit heaters, riser is not built.
|