INSP-Final Inspection | 10/20/2008 | 10/20/2008 | 10/20/2008 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 10/14/2008 | 10/15/2008 | 10/15/2008 | P | FAIL |
Troy Cobbley
|
|
|
Provide sticker on bell, provide inspection tag on riser, hydraulic sticker, space heads and cover the plastic supply piping and the cpvc riser piping as discussed. It does not appear that the underground supply has been flushed either.
|
INSP-Supply line flush | 10/14/2008 | 10/15/2008 | 10/15/2008 | A | FAIL |
Troy Cobbley
|
|
|
Provide sticker on bell, provide inspection tag on riser, hydraulic sticker, space heads and cover the plastic supply piping and the cpvc riser piping as discussed. It does not appear that the underground supply has been flushed either.
|
INSP-Sprinkler Rough-in/Hydro | 8/1/2008 | 8/4/2008 | 8/4/2008 | A | PASS |
Troy Cobbley
|
|
|
The tenting has been modified and the piping can now be covered. Todd was in the process of lowering the two garage sidewall heads. I will verify them at the final.
|
INSP-Sprinkler Rough-in/Hydro | 7/31/2008 | 8/1/2008 | 8/1/2008 | A | FAIL |
Troy Cobbley
|
|
|
The tenting in the master bedroom and the master closet need modified to provide better tenting. The two sidewall heads now have the correct coverage but are too close to the ceiling. I contacted Todd and let him know the situation.
|
INSP-Sprinkler Rough-in/Hydro | 7/29/2008 | 7/29/2008 | 7/29/2008 | P | PART |
Troy Cobbley
|
|
|
Rough to cover Inspection is basically passed but as-builts are needed to show the supply piping changes from the basement to the second floor and the added head at the top of the stairs. Also the standard coverage sidewall heads in the garage are overspaced.
|