INSP-Final Inspection | 6/25/2009 | 6/30/2009 | 6/30/2009 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled. The forward flush passed.
|
INSP-Final Inspection | 3/4/2009 | 3/5/2009 | 3/5/2009 | A | FAIL |
Troy Cobbley
|
|
|
This permit will be ok to final when the fire alarm interconnects have been verified.
|
INSP-Sprinkler Rough-in/Hydro | 2/17/2009 | 2/18/2009 | 2/18/2009 | P | PASS |
Troy Cobbley
|
|
|
The above ground hydo test for the new east addition passed.
|
INSP-Sprinkler Rough-in/Hydro | 2/10/2009 | 2/11/2009 | 2/11/2009 | A | PASS |
Troy Cobbley
|
|
|
Underground flush passed. See city approved plans for locations of sidewalls in entrance pockets are ok to cover
|
INSP-Sprinkler Rough-in | 1/27/2009 | 1/28/2009 | 1/28/2009 | A | PASS |
Troy Cobbley
|
|
|
See the city approved plans for the sprinkler piping on the first floor, at the entry lobby, that can be covered. It has todays date 1/28/2009.
|
INSP-Sprinkler Rough-in | 1/12/2009 | 1/13/2009 | 1/13/2009 | A | PASS |
Troy Cobbley
|
|
|
The north east facing canopy can be covered.
|
INSP-Sprinkler Rough-in | 1/8/2009 | 1/9/2009 | 1/9/2009 | A | PASS |
Troy Cobbley
|
|
|
The two east side outside canopies are ok to cover.
|
INSP-Sprinkler Rough-in | 1/6/2009 | 1/6/2009 | 1/6/2009 | P | PASS |
Troy Cobbley
|
|
|
The sprinkler piping in the upper level of the new east entry lobby can be covered. Plan resubmittals are required showing the piping changes. I spoke to Tom with Viking about this.
|
INSP-Supply line flush | 12/8/2008 | 12/9/2008 | 12/9/2008 | A | PASS |
Troy Cobbley
|
|
|
This inspection was actually for an underground hydro not an underground flush. The hydro test passed.
|
INSP-Sprinkler Rough-in/Hydro | 10/10/2008 | 10/13/2008 | 10/13/2008 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans with todays date for locations where the sprinkler piping can be covered.
|
INSP-Sprinkler Rough-in/Hydro | 10/9/2008 | 10/9/2008 | 10/9/2008 | P | FAIL |
Forrest France
|
|
|
Trapeeze hangers at the lower level branch lines in the south office and delivery rooms are not approved (sidewinder sammys in the narrow dimention), discussed main and branchline changes to be shown on resubmittals prior to project final. See stamped plan set for location inspected today.
|
INSP-Sprinkler Rough-in | 8/21/2008 | 8/22/2008 | 8/22/2008 | P | PASS |
Troy Cobbley
|
|
|
This inspection was for the underground supply cover. The two 45 elbows have been replaced with a single 90 elbow. The piping is approved for cover.
|