INSP-Final Inspection | 1/8/2009 | 1/9/2009 | 1/9/2009 | A | PASS |
Troy Cobbley
|
|
|
Permit finaled. Forward flush also passed.
|
INSP-Sprinkler Rough-in/Hydro | 12/15/2008 | 12/16/2008 | 12/16/2008 | P | PASS |
Troy Cobbley
|
|
|
The remaining hydro tests passed.
|
INSP-Sprinkler Rough-in/Hydro | 12/8/2008 | 12/9/2008 | 12/9/2008 | A | PASS |
Troy Cobbley
|
|
|
The second floor hydro test passed. The first floor hydro test failed.
|
INSP-Sprinkler Rough-in | 12/3/2008 | 12/4/2008 | 12/4/2008 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for the deficiencies that have been corrected on the first and second floors. I pointed out to Charles that the FDC is possibly located too close to the roof rain gutter and side of the building.
|
INSP-Sprinkler Rough-in | 11/20/2008 | 11/21/2008 | 11/21/2008 | P | FAIL |
Forrest France
|
|
|
See red lines on plan set for areas in need of correction (2nd floor only inspected today) including an obstructed head at a janitors room, one missing arm-over hanger, heads overspaced at the restrooms, six overspaced heads at the southeast lounge room.
|
INSP-Sprinkler Rough-in | 10/15/2008 | 10/20/2008 | 10/20/2008 | A | PART |
Troy Cobbley
|
|
|
See the city approved plans for the locations of the defieciencies. Only the rooms on the first floor that do not have red correction marks in them can be covered. No rooms on the second floor can be covered. As-builts need to be provided prior to a final inspection which show all of the changes as marked on the city approved plans.
|