INSP-Final Inspection | 12/19/2008 | 12/19/2008 | 12/19/2008 | P | PASS |
Forrest France
|
|
|
C/N items verified for completion, fire sprinkler permit finaled.
|
INSP-Sprinkler Rough-in/Hydro | 12/16/2008 | 12/16/2008 | 12/16/2008 | P | FAIL |
Forrest France
|
|
|
Two heads at a meeting room need relocated, one head at a storage room is overspaced, annotated areas on plans approved for cover with today's date.
|
INSP-Sprinkler Rough-in | 12/2/2008 | 12/3/2008 | 12/3/2008 | P | PART |
Forrest France
|
|
|
Okay to cover pendent heads at the new entry vestibule, one additional pendent at the reception area soffit also okayed.
|
INSP-Sprinkler Rough-in | 11/18/2008 | 11/18/2008 | 11/18/2008 | A | PART |
Forrest France
|
|
|
Site verified relocated head at an exam room and one additional head installed at the common corridor vestibule per plans.
|
INSP-Final Inspection | 11/14/2008 | 11/17/2008 | 11/17/2008 | P | PART |
Forrest France
|
|
|
Noted correction items finished.
|
INSP-Final Inspection | 11/13/2008 | 11/14/2008 | 11/14/2008 | A | FAIL |
Forrest France
|
|
|
Noted obstructed pendent head at exam room 124, missing one head to be added per approved drawings at the hallway vestibule, see locations annotated on stamped plan set.
|
INSP-Sprinkler Rough-in | 11/7/2008 | 11/10/2008 | 11/10/2008 | P | PASS |
Troy Cobbley
|
|
|
See the city approved plans for locations where the sprinkler piping can be covered. It will have todays date and my signature.
|
INSP-Sprinkler Rough-in/Hydro | 10/28/2008 | 10/28/2008 | 10/28/2008 | A | PART |
Forrest France
|
|
|
OH system modifications approved as noted on plans to date.
|
INSP-Sprinkler Rough-in | 10/24/2008 | 10/24/2008 | 10/24/2008 | P | PART |
Forrest France
|
|
|
See city approved plans for areas OK to cover. KR
|
INSP-Final Inspection | 9/25/2008 | 9/25/2008 | 9/25/2008 | P | PART |
Forrest France
|
|
|
OH rough-in for the "sleers" area only completed today, circled locations on plans approved for cover, noted one head at the reception counter soffit to be added per drawings, flex-head resubmittals verified.
|
INSP-Sprinkler Rough-in/Hydro | 9/11/2008 | 9/12/2008 | 9/12/2008 | A | FAIL |
Forrest France
|
|
|
Need to provide documentation addressing the installation of flex type head connections is approved. See item # 13 on the plan review for details. Overhead cover at the drop ceilings is not allowed at this time.
|