DOC - Permit Finaled | | | 8/7/2009 | | DONE |
|
|
|
|
INSP-Sprinkler Rough-in/Hydro | 8/19/2008 | 8/20/2008 | 8/20/2008 | P | PASS |
Troy Cobbley
|
|
|
The two additional upright heads have been added both restroom sprinkler piping can be covered.
|
INSP-Final Inspection | 8/19/2008 | 8/19/2008 | 8/20/2008 | A | PASS |
Sam Rogers
|
|
|
|
INSP-Sprinkler Rough-in/Hydro | 8/18/2008 | 8/19/2008 | 8/19/2008 | A | FAIL |
Troy Cobbley
|
|
|
Additional upright protection is required along the duct work in the south restroom. The north restroom is ok to cover.
|