INSP-Final Inspection | 2/9/2009 | 2/9/2009 | 2/9/2009 | P | PASS |
Troy Cobbley
|
|
|
permit finaled
|
INSP-Conference | 1/7/2009 | 1/7/2009 | 1/7/2009 | P | DONE |
Troy Cobbley
|
|
|
I spoke to Brian Johnson and to Andy, the builder, about the PIV that was shown to be installed on the overhead sprinkler plans has not been installed. Per the separate underground permit FIR08-00514 no PIV was being installed. The PIV needs to be installed, a wall PIV approved by the city of boise installed or the one hour room with exterior access provided. Brian stated that he would contact me with a solution.
|
INSP-Sprinkler Rough-in | 12/23/2008 | 12/23/2008 | 12/23/2008 | P | FAIL |
Forrest France
|
|
|
Wrong permit number request, intended for Tenant Improvement work.
|
INSP-Sprinkler Rough-in | 11/13/2008 | 11/14/2008 | 11/14/2008 | A | PART |
Forrest France
|
|
|
Reinspection for adjusted upright head locations in the truss webs at the roof deck passed. Noted three non-sprinklered concealed spaces at the SW round- locations marked on plans- in need of coverage or meet exceptions per NFPA.
|
INSP-Sprinkler Rough-in | 11/12/2008 | 11/14/2008 | 11/13/2008 | A | CANC |
Troy Cobbley
|
|
|
Your contact is Richard. Thanks. Phone #: ###-#### Internet Inspection Request from: Stan Beus Inspection cancelled from web by: Stan Beus
|
INSP-Sprinkler Rough-in | 11/4/2008 | 11/5/2008 | 11/5/2008 | A | PASS |
Troy Cobbley
|
|
|
The east exterior canopy can be covered now that the piping type and sizing has been corrected.
|
INSP-Sprinkler Rough-in/Hydro | 10/31/2008 | 11/3/2008 | 11/3/2008 | A | PASS |
Troy Cobbley
|
|
|
Above ground hydro test passed.
|
INSP-Sprinkler Rough-in/Hydro | 10/29/2008 | 10/31/2008 | 10/31/2008 | A | CANC |
Troy Cobbley
|
|
|
Per Charles the hydro test is to be cancelled.
|
INSP-Sprinkler Rough-in | 10/30/2008 | 10/31/2008 | 10/31/2008 | A | PART |
Troy Cobbley
|
|
|
The southwest canopy can be covered. The east canopy can not be covered due to cpvc piping being installed where as the plans indicate steel piping is to be installed. Plans either need to be resubmitted or piping is to be installed as per the plans. Also the upright sprinkler heads through out the rest of the building have not been installed as per NFPA 13 8.6.5.2.1.6 and exhibit 8.20. The general contractor also stated that he would install insulation in the eaves of the tower located on the southwest corner of the building. This space is considered a combustible concealed space.
|
INSP-Sprinkler Rough-in | 10/29/2008 | 10/30/2008 | 10/30/2008 | P | NR |
Forrest France
|
|
|
|