INSP-Final Inspection | 11/4/2008 | 11/4/2008 | 11/5/2008 | P | PASS |
Forrest France
|
|
|
Fire sprinkler permit passed final inspection.
|
INSP-Sprinkler Rough-in/Hydro | 11/3/2008 | 11/4/2008 | 11/4/2008 | A | PART |
Forrest France
|
|
|
OH fire sprinkler system modifications completed acceptable per the scope of work, noted one leak repaired while on site, one existing non-compliant head at the 2nd floor to be removed prior to final.
|
INSP-Sprinkler Rough-in/Hydro | 11/3/2008 | 11/3/2008 | 11/3/2008 | P | PART |
Forrest France
|
|
|
Okay for cover at the 2nd floor office room ceiling.
|
INSP-Sprinkler Rough-in/Hydro | 10/30/2008 | 10/30/2008 | 10/30/2008 | P | PART |
Forrest France
|
|
|
Sprinkler installation at the 2nd floor hard lid ceiling above the stairway is approved for cover, minor adjustments made while on site, see plans for locations okayed wtih todays date.
|