INSP-Final Inspection | 6/9/2009 | 6/10/2009 | 6/10/2009 | A | PASS |
Troy Cobbley
|
|
|
permit passed
|
INSP-Final Inspection | 6/8/2009 | 6/9/2009 | 6/9/2009 | A | FAIL |
Troy Cobbley
|
|
|
All items tested ok except for the hvac interconnect has not been terminated. The curtains in the south east room rolled up under alarm but the curtains in the main library room did not. Another inspection fee is to be applied.
|
INSP-Final Inspection | 6/6/2009 | 6/8/2009 | 6/8/2009 | A | FAIL |
Troy Cobbley
|
|
|
I arrived at the project and was notified by mark that the monitoring had not been set up/finalized with Apex. A re-inspection fee has been applied for any future inspections.
|
INSP-Final Inspection | 6/3/2009 | 6/4/2009 | 6/5/2009 | A | FAIL |
Troy Cobbley
|
|
|
No inspection was performed. The monitoring had not been set up completely, manual pull stations are mounted too high, door holders had not been completely installed and wired into the fire alarm panel, an hvac control wire was not connected to the panel yet and an electrical/fire alarm box behind the wet sprinkler riser did not have a cover installed. These are just items noted initially and is not a complete list of possible corrections needed.
|
FIR-Aging Inspection | 12/19/2008 | 12/19/2008 | 12/19/2008 | | DONE |
Forrest France
|
|
|
Building construction underway, work in progress.
|