INSP-Final Inspection | 1/29/2009 | 1/29/2009 | 1/29/2009 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 1/27/2009 | 1/28/2009 | 1/28/2009 | P | CANC |
Troy Cobbley
|
|
|
The resubmitted drawings have not been approved yet.
|
INSP-Final Inspection | 1/26/2009 | 1/27/2009 | 1/27/2009 | A | FAIL |
Troy Cobbley
|
|
|
Per Brian Johnson the remote area #4 will not work with the two additional elbows that have been added. He is to work out a solution and meet with Tim Frost and get an approval on the solution.
|
INSP-Final Inspection | 1/26/2009 | 1/26/2009 | 1/26/2009 | P | FAIL |
Troy Cobbley
|
|
|
The forward flow test passed inspection. The forward flow/FDC assembley did not pass inspection and needs to be installed as per the drawings. Two 3" 90's have been installed at the base of the riser. It appears per the drawings that a very slim safety factor was acheived on remoted area #4. I need verification that the 5% requirement is still satisfied. Ceiling tile needs to be removed where additional hangers were required for the pendant heads. The third floor roof access room needs a ceiling and a pendant, walls to the deck or upright protection needs to be provided throughout the third floor attic space.
|
INSP-Sprinkler Rough-in/Hydro | 10/8/2008 | 10/10/2008 | 10/9/2008 | P | DEFR |
Forrest France
|
|
|
Duplicate inspection request, see notes dated 10/8 and 10/9.
|
INSP-Sprinkler Rough-in/Hydro | 10/8/2008 | 10/9/2008 | 10/9/2008 | A | PART |
Forrest France
|
|
|
OH hydrostatic testing for the 1st, 2nd and 3rd floor piping completed acceptable.
|
INSP-Sprinkler Rough-in/Hydro | 10/7/2008 | 10/8/2008 | 10/8/2008 | P | FAIL |
Forrest France
|
|
|
Lacking coverage at both the north and south stairway landings 1st floor, seismic bracing at two locations is not approved including at the riser and the 3rd floor. See locations marked on plans.
|