INSP-Final Inspection | 11/3/2008 | 11/4/2008 | 11/4/2008 | A | PASS |
Forrest France
|
|
|
Items on C/N finished, fire alarm work passed field inspection, permit finaled.
|
INSP-Final Inspection | 11/3/2008 | 11/3/2008 | 11/3/2008 | P | FAIL |
Forrest France
|
|
|
Need to provide signage at the door to the relocated FACP room, missing three junction box covers-two at the 2nd floor one at the 1st floor, noted the outside sprinkler waterflow bell is not functional. Notification, manual pulls, signals recieved, nac and main panel tested okay.
|
INSP-Final Inspection | 10/31/2008 | 10/31/2008 | 10/31/2008 | P | NR |
Forrest France
|
|
|
This job was not ready to be inspected. Panel was in trouble due to close tampers, existing wires that were not being used and were not for future devices needs to be removed.They will call in for an am inspection so we can test devices in existing bussiness due to relocation of panel. kr
|
INSP-Final Inspection | 10/30/2008 | 10/30/2008 | 10/30/2008 | P | NR |
Forrest France
|
|
|
Noted trouble at the panel due to nac fault, three sprinkler tampers closed due to work in progress,system is not ready for final inspection at this time.
|