Permit Information
Permit NumberFIR08-00626
StatusFinaled
Name DEBEST FIRE PROTECTION
Site Address 650 N ARMSTRONG PL
Project NameWINCO
Customer Number 
ePlanReview 
Description
Revised FIR Scope of:
Added 17 heads for as built changes. The heads were added for new wall configuration changes and hip sprinklers were added in the canopy to accommodate combustible construction.

Revised FIR Scope:
The UG scope of work begins from an existing 8” C-900 line stubbed onto the property by others off of the 12’ loop as required. A second set of calculations for the record storage area has been provided. These revisions have been noted on the plan as Revision A and dated 09/23/08.
FIR Scope:
The UG scope of work begins from an existing 8” C-900 line stubbed onto the property by others. From there, run 110’ of 6” C900 out and rise up into a 1 hour rated riser room with in a new 40,737-ft/2 one story structure. The supply will be controlled remotely from a PIV. The FDC will also be remote of the Bldg. to serve only the new addition.
The OH fire sprinkler scope of work includes installing a complete wet pipe sprinkler system through out the accordance with NFPA 13. Work in the existing area included relocating, adding and deleting heads to accommodate a new ceiling layout where indicated on sheet FP-3 of 4. All work in the existing area is limited to the clouded areas. The fire sprinkler work shall comply with NFPA 13-2007, NFPA 24-2002 the IFC-2006,
The fire sprinkler system work shall comply with IFC 2006, attached review comment and conditions list, as regulated by the Fire Chief. These notes, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to permit BLD08-01127.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection1/28/20091/29/20091/29/2009APASS
DetailsTroy Cobbley
Permit finaled
INSP-Sprinkler Rough-in/Hydro1/28/20091/28/20091/28/2009PPASS
DetailsTroy Cobbley
The underground and overhead hydro tests passed.
INSP-Sprinkler Rough-in/Hydro1/26/20091/26/20091/27/2009PPASS
DetailsTroy Cobbley
The remaining ceilings covering the sprinkler piping are ok to install
INSP-Sprinkler Rough-in/Hydro1/21/20091/21/20091/22/2009PPART
DetailsTroy Cobbley
UG supply hydro failed. UG fdc hydro passed.
INSP-Sprinkler Rough-in1/20/20091/20/20091/20/2009PPASS
DetailsTroy Cobbley
See the city approved plans for the rooms where sprinkler piping can be covered.
INSP-Sprinkler Rough-in/Hydro1/15/20091/15/20091/15/2009PPASS
DetailsTroy Cobbley
See the city approved plans for the Storage area that the sprinkler piping is ok to cover.
INSP-Sprinkler Rough-in/Hydro1/13/20091/13/20091/13/2009PPASS
DetailsTroy Cobbley
See the city approved plans for areas that are ok to cover
INSP-Sprinkler Rough-in/Hydro1/6/20091/6/20091/6/2009PPASS
DetailsTroy Cobbley
Hard Lids over the south restrooms are ok to install. The supply line for the FDC flushed passed.
INSP-Sprinkler Rough-in/Hydro12/30/200812/30/200812/30/2008PPASS
DetailsTroy Cobbley
The mens and womens locker rooms located along the north wall are ok to cover.
INSP-Sprinkler Rough-in/Hydro12/29/200812/29/200812/29/2008PPART
DetailsTroy Cobbley
The rough-in inspection for the 3" and 2 1/2" mains and 1 1/4" branchline piping passed. Pendant head locations have not been inspected at this time. Per the fitter plans are being resubmitted for pendant head location changes due to revised wall layout. I noted sprinkler coverage missing in four shower areas.
INSP-Sprinkler Rough-in/Hydro12/23/200812/26/200812/26/2008PDEFR
DetailsForrest France
Rough In Inspection - Contact: Todd K Phone #: ###-#### x1234 Internet Inspection Request from: Alicia Pauley
INSP-Supply line flush12/5/200812/8/200812/8/2008APART
DetailsTroy Cobbley
The flush for the underground supply line passed but the supply line for the remote FDC has not been flushed as required.
INSP-Sprinkler Rough-in10/1/200810/1/200810/1/2008PPASS
DetailsTroy Cobbley
The remaining underground piping is ok to cover.
INSP-Sprinkler Rough-in9/30/20089/30/20089/30/2008PPART
DetailsTroy Cobbley
The undergournd supply piping and the remote FDC piping is ok to cover except for either end since thrust blocks and vaults had not been installed yet. The PIV is being installed rather close to the parking lot curbing. I spoke to Dave Hanniman and did a on site visit. At this stage of the installation it does not look like the PIV will be in danger of being struck by a vehicle which is daves concern. Randy Bowron spoke to Chris Palmer with ESI about the concerns with the actual placement of the curbing and where it needs to be.
INSP-Sprinkler Rough-in/Hydro9/29/20089/29/20089/29/2008PCANC
DetailsTroy Cobbley
To be rescheduled per Todd.