INSP-Final Inspection | 5/21/2009 | 5/21/2009 | 5/21/2009 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Sprinkler Rough-in/Hydro | 5/19/2009 | 5/19/2009 | 5/19/2009 | P | CANC |
Troy Cobbley
|
|
|
Canceled due to the project related fire alarm system/permit not being complete. The backflow preventor has been certified. The fire alarm interconnections need to be tested/verified for final.
|
INSP-Final Inspection | 5/14/2009 | 5/18/2009 | 5/18/2009 | A | FAIL |
Troy Cobbley
|
|
|
Forward flush passed. Project was not finaled due to the fire alarm permit was not ready for inspection and questions regarding the standpipe flow as per note 42 of the review comments was an issue. Also the backflow preventor needs to be certified.
|
INSP-Sprinkler Rough-in | 4/8/2009 | 4/8/2009 | 4/8/2009 | P | PASS |
Troy Cobbley
|
|
|
The second and third floor sprinkler rough-in passed.
|
INSP-Sprinkler Rough-in/Hydro | 4/7/2009 | 4/8/2009 | 4/8/2009 | A | PASS |
Troy Cobbley
|
|
|
The overhead hydro test passed.
|
INSP-Sprinkler Rough-in | 3/9/2009 | 3/9/2009 | 3/9/2009 | P | PASS |
Troy Cobbley
|
|
|
The sprinkler piping above the ceiling in the third floor central stair tower is ok to cover.
|
INSP-Supply line flush | 3/4/2009 | 3/9/2009 | 3/9/2009 | P | PASS |
Troy Cobbley
|
|
|
The underground flush passed.
|
INSP-Sprinkler Rough-in/Hydro | 3/3/2009 | 3/4/2009 | 3/4/2009 | P | CANC |
Troy Cobbley
|
|
|
UG Hydro Phone #: ###-#### x1234 Internet Inspection Request from: Alicia Pauley
|
INSP-Sprinkler Rough-in/Hydro | 3/2/2009 | 3/3/2009 | 3/4/2009 | P | PART |
Troy Cobbley
|
|
|
UG Hydro passed. The rough-in inspection of the first and second floors did not pass. The problem is alot of pendant heads were designed to be installed under duct work and they ended up not being installed under the duct work and/or the duct work has been moved. The heads now exceed 22" from the deck. The pipe size, hangers and earthquaking is ok. The third floor, standpipes and riser has not been inspected.
|
INSP-Sprinkler Rough-in/Hydro | 12/12/2008 | 12/12/2008 | 12/12/2008 | P | CANC |
Troy Cobbley
|
|
|
UG Hydro Test - Contact: Dave Phone #: ###-#### x1234 Internet Inspection Request from: Alicia Pauley
|
INSP-Supply line flush | 12/10/2008 | 12/11/2008 | 12/11/2008 | P | CANC |
Troy Cobbley
|
|
|
This was for a hydro test and is to be cancelled per Dave.
|
INSP-Sprinkler Rough-in | 10/27/2008 | 10/27/2008 | 10/28/2008 | P | PASS |
Troy Cobbley
|
|
|
The underground supply piping is ok to cover and has been installed per plan.
|