Permit Information
Permit NumberFIR08-00699
StatusFinaled
Name ABSOLUTE FIRE PROTECTION
Site Address 1609 S OWYHEE ST
Project NameWhitney Elementary School
Customer Number 
ePlanReview 
Description
OH Scope:
Beginning from an existing 6” supply located with the 1 hour rated riser room, install a 4” vertical wet riser with two systems to serve through out the entire 60,770 ft/2 structure. The fire sprinkler system work shall comply with the IFC 2006, the attached review comments/conditions, as regulated by the Fire Chief. The review comments/conditions, permit and fire "Inspection Card" are required to be on site as a condition of this work, to provide witness of compliance verification of minimum code. This permit is attached to BLD06-01105 & UG permit FIR08-00631.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection10/27/200910/27/200910/27/2009PPASS
DetailsForrest France
Fire sprinkler permit work final approved.
INSP-Sprinkler Rough-in10/15/200910/15/200910/15/2009PFAIL
DetailsTroy Cobbley
The inspection was for the new dental area. The plans show three extended coverage pendants in this area but standard coverage have been installed instead. I was ok with this since it is not a remote area and coverage seems adequate. The problem is two wood beams have been installed above the ceiling where the upright protection has been removed. Sam Ball, myself and the general contractor talked about options.
INSP-Final Inspection8/18/20098/18/20098/19/2009PPASS
DetailsForrest France
Sprinkler monitoring, forward flow, C/N items, final walkthrough passed, contractor to call in UG permit for final as discussed, one missing escutcheon installed while on site, head guards at the mezzanine to be in place prior to building final, unfinished dentist office protected with uprights at the deck and provided with area separation.
INSP-Final Inspection8/17/20098/17/20098/18/2009PNR
DetailsForrest France
Project related fire alarm permit work is not ready for testing.
INSP-Sprinkler Rough-in8/11/20098/12/20098/12/2009APART
DetailsForrest France
Completed inspection for mechanical mezzanine areas, protection at entry overbuilds, storage rooms, and the dental office. Need to adjust upright coverage at the dental office and provide area separation at the east wall for interm shell protection, adjust one blocked upright at the mech. catwalk, discussed items for final including forward flow, riser supervison, final walkthrough, etc.
INSP-Sprinkler Rough-in8/11/20098/11/20098/12/2009PPART
DetailsForrest France
mike Phone #: ###-####
INSP-Conference8/10/20098/10/20098/10/2009ADONE
DetailsForrest France
Regarding items needed for project finals.
INSP-Sprinkler Rough-in/Hydro7/20/20097/20/20097/20/2009PPART
DetailsForrest France
Overhead hydrostatic testing for both wet systems at the riser manifold passed.
INSP-Sprinkler Rough-in/Hydro7/17/20097/20/20097/20/2009APART
DetailsForrest France
Overhead install at the kitchen area drop ceilings approved for cover, need to foam dry pendent penetrations at the freezer, non-sprinklered cavity at the east side exterior canopy verified for insulation fill per NFPA exception allowed.
INSP-Sprinkler Rough-in6/22/20096/22/20096/22/2009PPART
DetailsForrest France
Initialed and dated plans where grid ceiling areas are approved for cover including the library and administration offices.
INSP-Sprinkler Rough-in6/9/20096/9/20096/11/2009PPART
DetailsForrest France
Classroom wings approved for drop ceiling cover, cafeteria and gym rough-in okayed, see plans for annotations.
INSP-Sprinkler Rough-in5/20/20095/21/20095/21/2009APART
DetailsForrest France
See notations marked on plans with initials and todays date for several rooms okayed for sheetrock ceiling cover first floor south side.
INSP-Sprinkler Rough-in4/22/20094/22/20094/22/2009PPART
DetailsForrest France
Inspection for overhead cover at attic branchlines and upright heads at the kitchen, multi-use, front office and mechanical areas okayed for cover-See annotations on plans with today's date. Seismic bracing not yet installed to be verified at next inspection. Discussed field changes at the gym due to ceiling finishes and record drawings to be provided.
INSP-Sprinkler Rough-in4/15/20094/16/20094/16/2009PPASS
DetailsTroy Cobbley
See the city approved plans for locations where the sprinkler piping is ok for cover. These locations will have todays date and my initials.
INSP-Sprinkler Rough-in3/17/20093/18/20093/18/2009APART
DetailsForrest France
See plans marked for rough-in inspection completed today including three seismic braces to be added as discussed.
INSP-Sprinkler Rough-in3/12/20093/13/20093/13/2009APART
DetailsForrest France
OH rough-in okayed at the administration area and hard lid ceilings per plan annotations marked with today's date.
INSP-Sprinkler Rough-in3/2/20093/3/20093/3/2009APART
DetailsForrest France
Inspection for overhead work at sheetrock ceilings in restrooms area "A" approved for cover-locations also marked on plans. Also discussed exceptions allowed per NFPA 13 for non-sprinklered canopies and concealed spaces at the exterior portions of the building.
INSP-Sprinkler Rough-in2/17/20092/18/20092/18/2009APART
DetailsForrest France
Rough-in approved for cover per red lines on sheet FP-3 (east classroom wing).
INSP-Sprinkler Rough-in1/30/20091/30/20091/30/2009PPART
DetailsForrest France
OH installation at classroom wing as marked on plan set sheet FP2 including exceptions okayed for cover.
FIR-Aging Inspection1/28/20091/28/20091/28/2009 DONE
DetailsForrest France
Work in progress.