INSP-Final Inspection | 6/9/2009 | 6/9/2009 | 6/9/2009 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled
|
INSP-Final Inspection | 6/5/2009 | 6/8/2009 | 6/8/2009 | A | CANC |
Troy Cobbley
|
|
|
The fire alarm system was not reading for testing.
|
INSP-Final Inspection | 6/5/2009 | 6/5/2009 | 6/5/2009 | P | FAIL |
Troy Cobbley
|
|
|
The interconnections with the fire alarm system could not be tested. The forward flow of the backflow preventor passed.
|
INSP-Sprinkler Rough-in | 4/10/2009 | 4/13/2009 | 4/13/2009 | A | PART |
Troy Cobbley
|
|
|
The sprinkler piping can be covered. See the city approved plans for the locations of three items that need corrected such as a blocked head, painted head and an overspaced head. Also there is no computer record of the plans being resubmitted due to a sprinkler main being modified/relocated in a remote area and theFDCbeing relocated. See the previous inspection entry for these items.
|
INSP-Sprinkler Rough-in/Hydro | 4/8/2009 | 4/10/2009 | 4/10/2009 | A | PASS |
Troy Cobbley
|
|
|
The overhead hydro test passed
|
INSP-Sprinkler Rough-in | 1/26/2009 | 1/26/2009 | 1/26/2009 | P | PART |
Troy Cobbley
|
|
|
The sprinkler rough-in is passed. Not all of the sprinkler drops have been installed. Final sprinkler spacing will need to be verified when drops, ceilings and soffits have been installed. The FDC has been relocated and a sprinkler main in a hydraulic remote area on the north side of the building has been rerouted. These changes will need to be verified by teh plan reviewer.
|