INSP-Final Inspection | 8/12/2009 | 8/13/2009 | 8/13/2009 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled.
|
INSP-Final Inspection | 7/28/2009 | 7/29/2009 | 7/30/2009 | P | FAIL |
Troy Cobbley
|
|
|
All of the initiating devices were tested but when it came time to verify signals nothing matched including the building address. All devices will need to be retested. All of the duct smoke detectors have been deleted as well as the dry pipe valve. As-builts are required. Strobe coverage is missing in the east lobby. It was addressed on the city approved plans but was not dealt with during installation. Strobe coverage had to be increased in a meeting room.
|
INSP-Final Inspection | 7/28/2009 | 7/28/2009 | 7/28/2009 | P | CANC |
Forrest France
|
|
|
Troy, Can we set this up for 3:00ish? Please call me as soon as you may know, so that I can set up the sprinkler guys. Thanks, Jason ###-#### Phone #: ###-#### Internet Inspection Request from: Jason Minnick Inspection cancelled from web by: Jason Minnick
|
INSP-Final Inspection | 7/28/2009 | 7/29/2009 | 7/28/2009 | A | CANC |
Troy Cobbley
|
|
|
Troy, Can we do this early in the morning? Please let me know as soon as possible, so I can set it up with the GC and the Sprinkler guys. Thanks, Jason ###-#### Phone #: ###-#### Internet Inspection Request from: Jason Minnick Inspection cancelled from web by: Jason Minnick
|
FIR-Aging Inspection | 5/19/2009 | 5/19/2009 | 5/19/2009 | | NR |
Troy Cobbley
|
|
|
Work is in progress.
|