INSP-Final Inspection | 4/14/2009 | 4/15/2009 | 4/15/2009 | P | PASS |
Troy Cobbley
|
|
|
Permit finaled. The underground flush passed. The contractor is to install a 1/2" plug on the outside alarm bell back box as discussed.
|
INSP-Final Inspection | 4/13/2009 | 4/13/2009 | 4/13/2009 | P | CANC |
Troy Cobbley
|
|
|
To be cancelled per Scott.
|
INSP-Sprinkler Rough-in/Hydro | 1/27/2009 | 1/28/2009 | 1/28/2009 | A | PASS |
Troy Cobbley
|
|
|
Per Scott the plans and hydraulic calculations are being resubmitted for 18'x18' spacing in the Recreation Room. Based on this conversation the sprinkler piping is ok to cover in this room. If the hydraulic calculations don't work additional heads will need to be added as per the original approved plans at the contractors expense.
|
INSP-Sprinkler Rough-in/Hydro | 1/20/2009 | 1/21/2009 | 1/21/2009 | A | PART |
Troy Cobbley
|
|
|
The sprinkler piping is ok to cover on both floors except for the first floor west entertainment room. The heads in this room are overspaced.
|
INSP-Sprinkler Rough-in | 1/20/2009 | 1/20/2009 | 1/20/2009 | P | CANC |
Troy Cobbley
|
|
|
To be rescheduled per the fitter.
|
INSP-Sprinkler Rough-in | 1/16/2009 | 1/20/2009 | 1/19/2009 | A | CANC |
Troy Cobbley
|
|
|
Rough to cover inspection please call 1 hour before inspection time. Javier is the contact ###-#### Phone #: ###-#### Internet Inspection Request from: Trent Bice Inspection cancelled from web by: Trent Bice
|
INSP-Sprinkler Rough-in/Hydro | 1/15/2009 | 1/16/2009 | 1/16/2009 | P | CANC |
Troy Cobbley
|
|
|
Rough to cover inspection has been rescheduled for tuesday. The project was not ready for inspection with tenting and piping needing completing.
|