Information based on query as of Wednesday, July 17, 2024.
Permit Information
Permit NumberFIR08-00766
StatusFinaled
Name TREASURE VALLEY FIRE PROTECTION
Site Address 2390 E FREIGHT ST
Project NameWinco Distribution Center
Customer NumberUDG ONLY
ePlanReview 
Description
Scope of Work: UG Only - The contractor oversee the complete underground scope of work by others, to include running a new 8” C-900 supply to the two out buildings, (Maintenance & Truck Return) with wall PIV main control valves. In addition, run 2050’ of 10” C900 and 1575’ of 12” C900 out to the main bldg and fire pump house. The contractor will install 11 yard PIV’s and supply lead-ins to the each bldg’s riser location as shown on sheet FP-1 dated 11/11/08.
The fire sprinkler underground work shall comply with NFPA 13-2007, NFPA 24-2007 the IFC-2006, attached review comment and conditions list, as regulated by the Fire Chief. These notes, permit and fire “Inspection Card” are required to be on site as a condition of this work, to provide witness of compliance verification of minimum fire code. This permit is attached to building permit: BLD07-02097. The overhead will be submitted under a separate permit.
Contact Information
See Activities list for contact information
Show All Activities
DescriptionReceivedRequestedCompletedAM/PMDispositionAssigned To 
INSP-Final Inspection8/20/20098/20/20098/21/2009PPASS
DetailsForrest France
Underground fire supply line permit work approved for final status.
INSP-Supply line flush4/3/20094/6/20094/6/2009APASS
DetailsForrest France
Completed UG supply line flush for system leads to the truck return building and maintenance building.
INSP-Sprinkler Rough-in/Hydro4/2/20094/2/20094/2/2009APART
DetailsForrest France
See dated plan notes for UG installation work okayed.
INSP-Sprinkler Rough-in/Hydro3/31/20094/1/20094/1/2009PPART
DetailsForrest France
Hydrostatic testing for UG supply lead in piping service to the truck return and maintenance buildings each completed satisfactory, maint. building service okayed within allowable leakage amounts per NFPA 13.
INSP-Sprinkler Rough-in3/31/20093/31/20093/31/2009APART
DetailsForrest France
Thrust blocking at the truck return building supply line okayed.
INSP-Supply line flush3/27/20093/30/20093/30/2009PPART
DetailsForrest France
See initials on plans for the last riser supply lead-in flush completed today serving the main building.
INSP-Sprinkler Rough-in3/30/20093/30/20093/30/2009PFAIL
DetailsForrest France
Thrust blocks at two 45 ells in the supply line to the SE detatched building are not of sufficient size or location, field changes in pipe routes must be shown on approved plans.
INSP-Supply line flush3/27/20093/30/20093/30/2009APART
DetailsForrest France
UG fire supply line flush for two east side riser lead-ins completed okay.
INSP-Supply line flush3/27/20093/27/20093/27/2009PPASS
DetailsTroy Cobbley
The south facing stub-in, located second from the east end, passed the underground flush.
INSP-Supply line flush3/26/20093/27/20093/27/2009APART
DetailsForrest France
UG fire supply line flush for the east half building service completed satisfactory, also flushed lead in to the SE corner riser. See approved plans for marked locations with today's date.
INSP-Sprinkler Rough-in/Hydro3/26/20093/26/20093/27/2009PPART
DetailsForrest France
UG fire supply line hydrostatic test for the east half of the building service passed- see marked area on approved plan set.
INSP-Supply line flush3/19/20093/19/20093/19/2009APART
DetailsForrest France
UG lead in flush for the 3rd to west riser as marked on approved plans completed okay.
INSP-Supply line flush3/16/20093/18/20093/18/2009APART
DetailsForrest France
UG flush completed satisfactory for the two far west system lead-ins, ( main supply line and the west main supply line included).
INSP-Sprinkler Rough-in/Hydro3/16/20093/17/20093/17/2009PNR
DetailsForrest France
Brian Phone #: ###-####
INSP-Sprinkler Rough-in/Hydro3/13/20093/16/20093/16/2009PPART
DetailsForrest France
UG fire supply line hydrostatic testing for the lead in to the pump house and the supply/feed to the west half of the building including three stubs passed within allowable leakage amounts per NFPA 13.
INSP-Sprinkler Rough-in/Hydro3/10/20093/11/20093/11/2009ANR
DetailsForrest France
Scheduled by a contractor via Hello! on 3/10/2009 at 12:59:03 PM. Contact: ###-####. NOTE: Hydrostatic test not ready per phone call from contractor.
INSP-Sprinkler Rough-in/Hydro3/3/20093/4/20093/4/2009PPASS
DetailsTroy Cobbley
See the onsite plans for the locations inspected today.
INSP-Sprinkler Rough-in/Hydro3/2/20093/3/20093/3/2009APART
DetailsForrest France
See approved plan set for locations of three thrust blocks at tee's feeding system risers okayed for cover marked with today's date.
INSP-Sprinkler Rough-in/Hydro3/2/20093/2/20093/3/2009PPART
DetailsForrest France
Verified thrust blocking at 45's adjacent to the storm drain at the Freight street entrance.
INSP-Sprinkler Rough-in/Hydro2/24/20092/25/20092/25/2009APASS
DetailsTroy Cobbley
This was a cover inspection at multiple areas of the underground supply piping. See the city approved plans for locations where the piping is ok to cover.
INSP-Sprinkler Rough-in/Hydro2/20/20092/24/20092/24/2009PCANC
DetailsTroy Cobbley
This is for cover inspection at 12" site feed at jobsite entrance and south center 12" near main bldg. Please call with time frame. Thank you Phone #: ###-#### Internet Inspection Request from: Jeff Packham Inspection cancelled from web by: Jeff Packham
INSP-Sprinkler Rough-in/Hydro2/18/20092/19/20092/19/2009APART
DetailsForrest France
See approved plans for underground fire supply line pipe runs okayed for cover, added 45's for change in bury depth below the storm drain adjacent to Freight Street to be indicated on as-builts, also need to verify thrust blocking/deadmans at top 45's prior to cover.
INSP-Sprinkler Rough-in/Hydro2/18/20092/18/20092/18/2009PDEFR
DetailsForrest France
This is for cover inspection at 12" site feed at jobsite entrance. Thrust blocks will be ready at 1:00 pm. If inspection does not fit schedule please disregard and complete tomorrow am. Thank you. Phone #: ###-#### Internet Inspection Request from: Jeff Packham
INSP-Sprinkler Rough-in/Hydro2/13/20092/13/20092/17/2009PPART
DetailsForrest France
See approved plans for locations okay for bury.
INSP-Sprinkler Rough-in/Hydro2/12/20092/12/20092/12/2009PNR
DetailsForrest France
Missing thrust blocks, seismic clearance at the riser SW corner is not sufficient, bolts at mech. tees and 90's need coated and covered.
INSP-Sprinkler Rough-in/Hydro2/4/20092/9/20092/7/2009PCANC
DetailsForrest France
Please call for time frame. This is cover inspection for underground. Phone #: ###-#### Internet Inspection Request from: Jeff Packham Inspection cancelled from web by: Jeff Packham
INSP-Sprinkler Rough-in/Hydro2/4/20092/5/20092/4/2009PCANC
DetailsForrest France
Please call with time frame for inspection. This is for undergound cover inspection at South East area of site. Phone #: ###-#### Internet Inspection Request from: Jeff Packham Inspection cancelled from web by: Jeff Packham
INSP-Sprinkler Rough-in2/2/20092/4/20092/4/2009APART
DetailsForrest France
Ductile riser and stub out connection to the yard PIV at the NE corner of the building okayed for cover, discussed bedding material install, noted PIV final adjustment to be provided at 3' above finish grade when complete, see stamped plan set for initials and location of work inspected today.
INSP-Sprinkler Rough-in/Hydro2/1/20092/3/20092/3/2009ANR
DetailsForrest France
Work underway for the portion of piping to be inspected-missing one 90, thrustblocks, etc., not ready at this time. Discussed AM inspection scheduled 2/4.
INSP-Sprinkler Rough-in/Hydro2/1/20092/2/20092/2/2009PCANC
DetailsForrest France
Cover inspection for portion of undergground. Please call and inform of time frame. Phone #: ###-#### Internet Inspection Request from: Jeff Packham
INSP-Sprinkler Rough-in/Hydro1/28/20091/29/20091/29/2009APART
DetailsForrest France
Thrust blocking at two 45 deg. ells at the SE corner of the building are approved for cover.
INSP-Sprinkler Rough-in/Hydro1/27/20091/28/20091/28/2009APART
DetailsForrest France
See stamped plan set for UG pipe runs okay to bury.
INSP-Sprinkler Rough-in1/27/20091/27/20091/27/2009PPART
DetailsForrest France
UG fire supply pipe per red-line annotations with todays date on approved plan set okayed for bury, (NE corner).
INSP-Sprinkler Rough-in1/14/20091/15/20091/15/2009APART
DetailsForrest France
See annotations initialed with today's date for location of two stubs and riser pieces okayed for cover at the south/central side of the building.
INSP-Sprinkler Rough-in1/12/20091/12/20091/12/2009PCANC
DetailsForrest France
brian Phone #: ###-#### Inspection cancelled from web by: Jeff Packham